13. Shipping and Navigation

13.1.   Introduction

13.1. Introduction

  1. This chapter of the Array Environmental Impact Assessment (EIA) Report presents the assessment of the likely significant effects (LSE1) (as per the EIA Regulations) on shipping and navigation as a result of the Ossian Array which is the subject of this application (hereafter referred to as “the Array”). Specifically, this chapter considers the potential impacts of and reaches a conclusion on the LSE1 arising from the Array on shipping and navigation during the construction, operation and maintenance, and decommissioning phases.
  2. The following technical chapters also inform the assessment presented in this chapter:
  • volume 2, chapter 12: Commercial Fisheries.
  1. This chapter summarises and is informed by the outputs of the Navigational Risk Assessment (NRA) (volume 3, appendix 13.1), which is the technical document required by the Maritime and Coastguard Agency (MCA) under Marine Guidance Note (MGN) 654 (MCA, 2021a) to provide a detailed assessment of shipping and navigation. Compliance with MGN 654 has been demonstrated via completion of an MGN 654 checklist included in the NRA. All relevant findings of the NRA are summarised in this chapter noting the full technical detail is provided in volume 3, appendix 13.1.

13.2.   Purpose of the Chapter

13.2. Purpose of the Chapter

  1. The Array EIA Report provides the Scottish Ministers, statutory and non-statutory stakeholders with the required information to determine the LSE1 of the Array on the receiving environment. This is further outlined in volume 1, chapter 1.
  2. The purpose of this shipping and navigation Array EIA Report chapter is to:
  • present the existing environmental baseline established from desk studies, site-specific surveys, numerical modelling studies and consultation with stakeholders;
  • identify any assumptions and limitations encountered in compiling the environmental information;
  • present the environmental impacts on shipping and navigation arising from the Array and reach a conclusion on the LSE1 on shipping and navigation, based on the information gathered and the analysis and assessments undertaken; and
  • highlight any necessary monitoring and/or mitigation measures which are recommended to prevent, minimise, reduce or offset the likely significant adverse environmental effects of the Array on shipping and navigation.

13.3.   Study Area

13.3. Study Area

  1. A 10 nm buffer has been applied around the site boundary (i.e. the area within which the Array is located) (hereafter referred to as the ‘shipping and navigation study area’), as presented in Figure 13.1   Open ▸ . This shipping and navigation study area has been defined to provide local context to the analysis of risks by capturing the relevant routes and vessel traffic movements within, and in proximity to, the Array. This is a standard radius for shipping and navigation, was agreed with the Scottish Ministers within the Ossian Array Scoping Opinion (MD-LOT, 2023) and has been used in the majority of United Kingdom (UK) offshore wind farm NRAs. It also aligns with the approach from the Array EIA Scoping Report (Ossian OWFL, 2023) and has been presented to key shipping and navigation stakeholders including at the Hazard Workshop for the Array (see section 13.5).
  2. Cumulative routeing within the NRA and cumulative effects assessment (CEA) in section 13.12 has been considered within a 50 nm buffer of the site boundary.

Figure 13.1:
Shipping and Navigation Study Area

Figure 13.1: Shipping and Navigation Study Area

13.4.   Policy and Legislative Context

13.4. Policy and Legislative Context

  1. Policy and legislation on renewable energy infrastructure is presented in volume 1, chapter 2 of the Array EIA Report. Policy and legislation specifically in relation to shipping and navigation is contained in:
  • United Nations Convention on the Law of the Sea (UNCLOS) (United Nations (UN), 1982);
  • Convention on the International Regulations for Preventing Collisions at Sea (COLREGs) (International Maritime Organization (IMO), 1972/77);
  • Safety of Life at Sea (SOLAS) Chapter V (IMO, 1974);
  • UK Marine Policy Statement (MPS) (HM Government, 2011);
  • Scotland’s National Marine Plan (NMP) (Scottish Government, 2015); and
  • Scotland’s Sectoral Marine Plan (SMP) for Offshore Wind Energy (Scottish Government, 2020).
  1. A summary of the legislative provisions relevant to shipping and navigation are provided in Table 13.1   Open ▸ , with other relevant policy provisions set out in Table 13.2   Open ▸ . These are summarised here with further detail presented in volume 3, appendix 13.1.

 

Table 13.1:
Summary of Legislation Relevant to Shipping and Navigation

Table 13.1: Summary of Legislation Relevant to Shipping and Navigation


Table 13.2:
Summary of Policy Relevant to Shipping and Navigation

Table 13.2: Summary of Policy Relevant to Shipping and Navigation

 

13.5.   Consultation

13.5. Consultation

  1. Table 13.3   Open ▸ presents a summary of the key issues raised during consultation activities undertaken to date specific to shipping and navigation for the Array and in the Ossian Array Scoping Opinion (MD-LOT, 2023) along with how these have these have been considered in the development of this shipping and navigation Array EIA Report chapter. Further detail is presented within volume 1, chapter 5.
Table 13.3:
Summary of Issues Raised During Consultation and Scoping Opinion Representations Relevant to Shipping and Navigation

Table 13.3: Summary of Issues Raised During Consultation and Scoping Opinion Representations Relevant to Shipping and Navigation

13.6.   Methodology to Inform Baseline

13.6. Methodology to Inform Baseline

  1. Desktop data sources, detailed in Table 13.4   Open ▸ , as well as site-specific vessel traffic survey data, detailed in Table 13.5   Open ▸ , have been reviewed and analysed to inform this shipping and navigation baseline. In addition, consultation with stakeholders via the Array EIA Scoping Report (Ossian OWFL, 2023) has been carried out to aid the collection of baseline information by establishing agreement on data sources. Data collection has followed the principles of and is compliant with MGN 654 (MCA, 2021a).

13.6.1.              Desktop Study

13.6.1. Desktop Study

  1. Information on shipping and navigation within the shipping and navigation study area was collected through a detailed desktop review of existing studies and datasets which are summarised in Table 13.4   Open ▸ . It is noted that MGN 654 (MCA, 2021a) compliant vessel traffic surveys have also been undertaken (section 13.6.2).
  2. Both general assessment of the data and numerical analysis using the datasets were used to characterise the baseline. The NRA (volume 3, appendix 13.1) includes full details of the analysis undertaken to develop the shipping and navigation baseline.

 

Table 13.4:
Data Sources Used to Inform the Shipping and Navigation Baseline

Table 13.4: Data Sources Used to Inform the Shipping and Navigation Baseline

 

13.6.2.              Site-Specific Surveys

13.6.2. Site-Specific Surveys

  1. Site-specific surveys were undertaken, as agreed with the MCA and the Northern Lighthouse Board (NLB) in a meeting on the 20 June 2022, and in compliance with MGN 654 (MCA, 2021a), to inform this chapter (see Table 13.3   Open ▸ for further details). A summary of the surveys undertaken used to inform the shipping and navigation assessment of effects is outlined in Table 13.5   Open ▸ .

 

Table 13.5:
Summary of Site-Specific Survey Data

Table 13.5: Summary of Site-Specific Survey Data

 

13.7.   Baseline Environment

13.7. Baseline Environment

13.7.1.              Overview of Baseline Environment

13.7.1. Overview of Baseline Environment

  1. The following sections provide a summary of the shipping and navigation baseline environment. The NRA (volume 3, appendix 13.1) includes full details of the analysis undertaken to develop the shipping and navigation baseline.
  2. Any proposed developments that have not yet begun construction are not considered baseline but have been considered cumulatively in section 13.12.

                        Navigational features

  1. A plot of navigational features in proximity to the Array is presented in Figure 13.2   Open ▸ based on the Admiralty Charts (UKHO, 2023) and Sailing Directions (UKHO, 2021).
  2. Three charted buoy positions are located within the site boundary, noting these are metocean buoys deployed on site. There are three additional aids to navigation in proximity to the site boundary, each equipped with an AIS transmitter; two inshore of the site boundary and within the shipping and navigation study area, and one offshore of the site boundary (approximately 1 nm outside of the shipping and navigation study area).
  3. There are charted wrecks and obstructions in vicinity of the site boundary, more commonly seen inshore. The closest is a charted wreck located 3 nm from the north-western corner of the site boundary, at an approximate depth of 67 m below Chart Datum (CD). Further details of wrecks, including non-charted wrecks which are not considered in this chapter, are provided in volume 2, chapter 19 (which classified two wrecks and one potential wreck in the Array).
  4. Seagreen 1 Offshore Wind Farm is the closest baseline offshore wind farm to the Array, located approximately 27 nm inshore of the site boundary.
  5. The Catcher Area Development (a development area, i.e. an area charted around some oil and gas fields) is charted approximately 21 nm to the east of the site boundary. Within the limits of this development area is the BW Catcher Floating, Production, Storage and Offloading (FPSO) unit with a chains and anchors zone surrounding it, as well as templates (subsea oil and gas infrastructure). A pipeline connecting to the FPSO exits the development area to its east.
  6. A subsea power cable lies south-east of the site boundary, at a minimum distance of approximately 19 nm.
  7. Further details on navigational features can be found in the NRA (volume 3, appendix 13.1).

                        Emergency response and incident overview

  1. The SAR helicopter service is operated by the Bristow Group, with the nearest base being located at Inverness Airport, approximately 113 nm north-west of the site boundary. A total of two helicopter taskings were located within the shipping and navigation study area between April 2015 and March 2023, with neither within the site boundary itself. This corresponds to an average frequency of one every four years.
  2. The closest RNLI station to the site boundary is at Aberdeen (approximately 44 nm to the north-west), where both an All-Weather Lifeboat (ALB) and Inshore Lifeboat (ILB) are in use. A total of three incidents were documented by the RNLI within the shipping and navigation study area between 2013 and 2022, corresponding to an average of one incident every three years. One of these incidents occurred within the site boundary, in 2016.
  3. A total of four incidents documented by the MAIB occurred within the shipping and navigation study area between 2012 and 2021, corresponding to an average of one incident every two to three years. Two of these incidents occurred within the site boundary, in 2015 and 2018.
  4. Further details on emergency response resources and maritime incidents can be found in the NRA (volume 3, appendix 13.1).

                        Vessel traffic movements

  1. A plot of vessel traffic survey data recorded within the shipping and navigation study area, colour-coded by vessel type, is presented in Figure 13.3   Open ▸ .
  2. During the winter survey period, an average of nine vessels per day was recorded within the shipping and navigation study area with two to three vessels per day recorded within the site boundary. During the summer survey period, an average of 11 vessels per day was recorded within the shipping and navigation study area with three to four vessels per day recorded within the site boundary.
  3. The most common vessel type across the 28 days was cargo, with four vessels per day within the shipping and navigation study area, followed by oil and gas, with three to four vessels per day. Fishing vessel and recreational vessel activity was low due to the distance of the Array offshore, which aligns with input received during consultation (see section 13.5). Within the shipping and navigation study area, there was one fishing vessel every two to three days (the majority of which were likely in transit based on speed and behaviour) and one recreational vessel every three to four days.
  4. There was broad correlation between the vessel traffic surveys and the long term data, i.e. oil and gas and cargo vessels being the most common vessel types, with minimal levels of fishing and recreational vessels.
  5. Using the principles of MGN 654 (MCA, 2021a), a total of 11 main commercial routes were identified from the long term data, presented in Figure 13.4   Open ▸ . The busiest routes were 1 and 2, which each comprised approximately two vessels per day. Routes 3 and 4 comprised approximately one vessel per day, all other routes comprised less than one vessel per day. 
  6. Detailed analysis of the vessel traffic data and the methodology behind the collection and preparation of this data are provided in the NRA (volume 3, appendix 13.1).

Figure 13.2:
Navigational Features in the Vicinity of the Array

Figure 13.2: Navigational Features in the Vicinity of the Array

Figure 13.3:
Vessels by Type (28 Days, Winter 2022 and Summer 2023)

Figure 13.3: Vessels by Type (28 Days, Winter 2022 and Summer 2023)

Figure 13.4:
Main Commercial Routes (Pre Wind Farm)

Figure 13.4: Main Commercial Routes (Pre Wind Farm)

13.7.2.              Future Baseline Scenario

13.7.2. Future Baseline Scenario

  1. The EIA Regulations require that “a description of the relevant aspects of the current state of the environment (baseline scenario) and an outline of the likely evolution thereof without implementation of the project, as far as natural changes from the baseline scenario can be assessed with reasonable effort on the basis of the availability of environmental information and scientific knowledge” is included within the Array EIA Report.
  2. If the Array does not come forward, an assessment of the ‘without development’ future baseline conditions has therefore also been carried out and is described within this section.
  3. For commercial vessels, potential future changes in traffic volumes are complex to predict, noting actual changes will be based on multiple factors including general market trends. Therefore, the NRA (volume 3, appendix 13.1) has considered two independent scenarios of potential growth in commercial vessel movements of 10% and 20%, with the outputs of this process accounted for within this chapter. It is likely that commercial vessels will deviate to avoid any other future wind farm developments that are under construction or in operation. This is in line with vessel behaviours observed at other UK offshore wind farms including Seagreen 1 Offshore Wind Farm and Neart na Gaoithe Offshore Wind Farm (Anatec, 2016).
  4. It should also be considered that there may be an increase in vessels associated with offshore wind farm construction and operation as further future wind farm developments are developed. Furthermore, fluctuations in oil and gas vessel activity will depend on future development and/or decommissioning, which again is heavily dependent on market conditions and is therefore difficult to predict. Precautionary future case assumptions have therefore been made with taking into account 10% and 20% increases in traffic.
  5. For commercial fishing and recreational vessel activity, there is similar uncertainty associated with long-term predictions given the limited reliable information on future trends upon which any firm assumptions can be made. Therefore, to ensure a conservative approach, 10% and 20% growth scenarios in commercial fishing vessel and recreational vessel movements have also been assumed in the NRA (volume 3, appendix 13.1).

13.7.3.              Data Limitations and Assumptions

13.7.3. Data Limitations and Assumptions

  1. Data limitations and assumptions are summarised below, with further details presented in the NRA (volume 3, appendix 13.1).

                        Automatic identification system data

  1. It is assumed that vessels under an obligation to broadcast information via AIS have done so, across all vessel traffic datasets. It has also been assumed that the details broadcast via AIS (such as vessel type and dimensions) are accurate unless clear evidence to the contrary was identified.

                        Historical incident data

  1. Although all UK commercial vessels are required to report incidents to the MAIB, this is not mandatory for non-UK vessels unless they are in a UK port, within UK territorial waters or carrying passengers to a UK port. There are also no requirements for non-commercial recreational craft to report incidents to the MAIB. Nevertheless, the MAIB incident database is considered to be a suitable source for the characterisation of historical incidents and adequate for the assessment.
  2. The RNLI incident data cannot be considered comprehensive of all incidents in the shipping and navigation study areas. Although hoax and false alarms are excluded, any incident to which a RNLI resource was not mobilised has not been accounted for in this dataset. Nevertheless, the RNLI incident data is considered to be a suitable source for the characterisation of historical incidents and adequate for the assessment.

                        United Kingdom Hydrographic Office Admiralty Charts

  1. The Admiralty charts published by the UKHO are updated periodically, and therefore the information shown may not reflect the real-time features within the region with total accuracy. Taking into account consultation undertaken, the characterisation of navigational features is considered to be suitably comprehensive and adequate for the assessment. For aids to navigation and wrecks/obstructions, only those charted and considered key to establishing the shipping and navigation baseline are shown.

13.8.   Key Parameters for Assessment

13.8. Key Parameters for Assessment

13.8.1.              Maximum Design Scenario

13.8.1. Maximum Design Scenario

  1. The Maximum Design Scenario (MDS) identified in Table 13.6   Open ▸ are those expected to have the potential to result in the greatest effect on an identified receptor or receptor group. These scenarios have been selected from the details provided in volume 1, chapter 3 of the Array EIA Report. Effects of greater significance are not predicted to arise should any other development scenario, based on details within the Project Description (volume 1, chapter 3) (e.g. different infrastructure layout), to that assessed here, be taken forward in the final design scheme.

 

Table 13.6:
Maximum Design Scenario Considered for Each Potential Impact as Part of the Assessment of LSE1 on Shipping and Navigation

Table 13.6: Maximum Design Scenario Considered for Each Potential Impact as Part of the Assessment of LSE1 on Shipping and Navigation

13.8.2.              Impacts Scoped Out of the Assessment

13.8.2. Impacts Scoped Out of the Assessment

  1. The shipping and navigation pre-Scoping workshop and the Array EIA Scoping Report (Ossian OWFL, 2023) process were used to facilitate stakeholder engagement on topics to be scoped out of the assessment (see Table 13.3   Open ▸ ).
  2. On the basis of the baseline environment and the Project Description outlined in volume 1, chapter 3 of the Array EIA Report, no impacts are proposed to be scoped out of the assessment for shipping and navigation. It is noted that impacts to vessel communication and position fixing equipment have been assessed in the NRA (volume 3, appendix 13.1), noting it has been considered within the assessment of collisions and allisions in section 13.11.

13.9.   Methodology for Assessment of Effects

13.9. Methodology for Assessment of Effects

13.9.1.              Overview

13.9.1. Overview

  1. The shipping and navigation assessment of effects has followed the Formal Safety Assessment (FSA) methodology since this is the internationally recognised approach for assessing the impact to shipping and navigation receptors, and is the approach required under the MCA’s methodology (Annex 1 of MGN 654). The following guidance documents have been considered:
  • MGN 654 (Merchant and Fishing) Safety of Navigation: Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response and its annexes (MCA, 2021a);
  • MGN 372 Amendment 1 (Merchant and Fishing) Guidance to Mariners Operating in the Vicinity of UK OREIs (MCA, 2022);
  • International Association of Marine Aids to Navigation and Lighthouse Authorities (IALA) O-139 on The Marking of Man-Made Offshore Structures (IALA, 2021a);
  • IALA G1162 The Marking of Offshore Man-Made Structures (IALA, 2021b);
  • The RYA Position on Offshore Renewable Energy Developments: Paper 1 (of 4) – Wind Energy (RYA, 2019a); and
  • Regulatory Expectations on Moorings for Floating Wind and Marine Devices (MCA and Health and Safety Executive (HSE), 2017).

13.9.2.              Criteria for Assessment of Effects

13.9.2. Criteria for Assessment of Effects

  1. The criteria for determining the likely significance of effects for shipping and navigation are derived from a two-stage process that considers the severity of consequence and frequency of occurrence. This section describes the criteria applied in this chapter to assign values to each of these two factors.
  2. The criteria for defining severity of consequence in this chapter are outlined in Table 13.7   Open ▸ . For the level of assistance required to manage environmental damage, the tiers indicated relate to the incident response matrix provided in the National Contingency Plan (NCP) (MCA, 2014).

 

Table 13.7:
Definition of Terms Relating to the Severity of Consequence (MCA, 2014)

Table 13.7: Definition of Terms Relating to the Severity of Consequence (MCA, 2014)

 

  1. The criteria for defining frequency of occurrence in this shipping and navigation Array EIA Report chapter are outlined in Table 13.8   Open ▸ .

 

Table 13.8:
Definition of Terms Relating to the Frequency of Occurrence

Table 13.8: Definition of Terms Relating to the Frequency of Occurrence

 

  1. The significance of the effect upon shipping and navigation is determined by correlating the severity of consequence and frequency of occurrence, as shown in in Table 13.9   Open ▸ .
  2. For the purposes of this assessment:
  • a level of effect of Unacceptable will be considered a ‘significant’ effect in terms of the EIA Regulations;
  • a level of effect of Broadly Acceptable will be considered ‘not significant’ in terms of the EIA Regulations; and
  • a level of effect of Tolerable will be considered ‘not significant’ in terms of the EIA Regulations assuming the risks have been reduced to As Low As Reasonably Practicable (ALARP) through application of mitigation.

Table 13.9:
Matrix Used for the Assessment of the Significance of the Effect

Table 13.9: Matrix Used for the Assessment of the Significance of the Effect

 

  1. Additionally, differences in terminology between this chapter (which uses EIA terminology) and the NRA (which uses FSA terminology) are summarised in Table 13.10   Open ▸ . Further details of the EIA methodology are provided in volume 1, chapter 6.

 

Table 13.10:
Summary of Differences in Terminology Between EIA and NRA

Table 13.10: Summary of Differences in Terminology Between EIA and NRA

 

13.10.            Measures Adopted as Part of the Array

13.10. Measures Adopted as Part of the Array

  1. As part of the Array design process, a number of designed in measures have been proposed to reduce the potential for impacts on shipping and navigation (see Table 13.11   Open ▸ ). They are considered inherently part of the design of the Array and, as there is a commitment to implementing these measures, these have been considered in the assessment presented in section 13.11 (i.e. the determination of significance assumes implementation of these measures). These designed in measures are considered standard industry practice for this type of development.

 

Table 13.11:
Designed in Measures Adopted as Part of the Array

Table 13.11: Designed in Measures Adopted as Part of the Array

 

13.11.            Assessment of Significance

13.11. Assessment of Significance

  1. Table 13.6   Open ▸ summarises the impacts arising from the construction, operation and maintenance and decommissioning phases of the Array, as well as the MDS against which each impact has been assessed. An assessment of the likely significance of the effects of the Array on the shipping and navigation receptors caused by each identified impact is given below.

Increased Vessel to Vessel Collision Risk Resulting from Displacement (ThirdParty to ThirdParty)

                        Construction phase

  1. There will be no restrictions on entry to the Array other than through any active safety zones. However, it is considered likely that commercial vessels will deviate to avoid the Array during construction, which will be marked as a buoyed construction area as directed by NLB. This aligns with input received in the Hazard Workshop including from commercial vessel representation, and operational experience of other UK wind farms including the nearby Seagreen 1 Offshore Wind Farm and Neart na Gaoithe Offshore Wind Farm.
  2. Anticipated deviations for the main commercial routes identified from the vessel traffic data have been defined. The full methodology for main route deviations is provided in volume 3, appendix 13.1, section 13.4.1, with reasonable worst case deviation assumptions established in line with industry experience and consultation feedback.
  3. Deviations from the pre wind farm scenario (current baseline) would be required for seven out of the 11 main commercial routes identified (routes 4, 5, 7, 8, 9, 10 and 12 as per Figure 13.4   Open ▸ ). However, it should be noted that the busiest routes (routes 4 and 5 in Figure 13.4   Open ▸ , which have six vessels per week and two to three vessels per week, respectively) would have very low deviation (less than 0.1 nm) while the routes with larger deviation (routes 7 and 8 in Figure 13.4   Open ▸ , which would have a deviation of 5.7 nm and 4.9 nm, respectively) are quieter routes (with only one to two vessels per week each). Further, worst case assumptions have been made in terms of deviations as set out in volume 3, appendix 13.1, section 13.4.1.
  4. It is noted that one regular commercial ferry operator was identified in the area, namely Smyril Line, who run a service between the Faroe Islands, Iceland and Rotterdam.
  5. With the main commercial route deviations in place, the base case annual vessel to vessel collision frequency for commercial vessels is estimated to be 5.42×10-4, corresponding to a return period of approximately one in 1,845 years. This represents a 31% increase in collision frequency compared to the pre wind farm base case scenario (see volume 3, appendix 13.1).
  6. The return period of one in 1,845 years is reflective of the low volume of vessel traffic in the area compared to elsewhere in the UK. Experience from previous under construction offshore wind farms indicates that Masters regularly choose to transit greater than 1 nm from construction works, and there is sufficient sea room available for vessels to do so around the Array (see volume 3, appendix 13.1).
  7. Smaller vessel types (e.g. fishing, recreation) may still choose to transit through the Array during construction, noting this would be at the discretion of individual vessels. In this regard it should be considered that there is limited experience of deployment of large scale floating offshore wind projects, and as such vessels may be less likely to transit through floating structures than those on fixed foundations (this assumption aligns with consultation input, see section 13.5). However, there is considered to be sufficient sea room to accommodate any vessels that chose to avoid the Array without notably increasing vessel density around the site boundary, given that the nearest baseline offshore wind farm (Seagreen 1 Offshore Wind Farm) is approximately 27 nm inshore of the Array.
  8. The impact will be present throughout the construction phase which will last for up to eight years. Given that third-party vessels are expected to be compliant with relevant Flag State regulations including the COLREGs, the likes of collision avoidance action seek to ensure that the likelihood of an encounter developing into a collision incident is low. This is furthered by the promulgation of information and charting of the buoyed construction area which will increase awareness of ongoing construction activities, thus allowing third-party vessels to passage plan in advance (see section 13.10).
  9. Based on the incident data studied for the NRA, the most likely consequences in the event of a collision incident between third-party vessels are minor contact between the vessels resulting in minor damage to property and minor reputational effects on business but no perceptible effect on people. Although considered less likely, collision between third party vessels could involve one of the vessels foundering resulting in Potential Loss of Life (PLL) and the environmental consequence of pollution. Such a scenario would be more likely if one of the vessels involved was a small craft which may have weaker structural integrity than a commercial vessel. The Array’s MPCP will be implemented to reduce the environmental impacts should pollution occur (volume 4, appendix 21, annex A).
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. Based on experience at existing operational offshore wind farms and consultation undertaken (see section 13.5), it is anticipated that commercial vessels will generally choose not to navigate internally within the Array. Therefore, the anticipated deviations discussed for the construction phase are directly applicable to the operation and maintenance phase, and it is likely that the deviations already established during construction will continue into the operation and maintenance phase. On this basis, the risk of third-party to third-party vessel collision for commercial vessels is considered analogous during the operation and maintenance phase as during the construction phase.
  2. It is anticipated that commercial fishing vessels and recreational vessels may choose to navigate internally within the Array (and this may be more likely during the operation and maintenance phase than in the construction phase given there will be no construction buoys or construction activities) based on experience at existing operational offshore wind farms, particularly in favourable weather conditions. Such navigation may result in an additional encounter and collision risk associated with these small craft exiting the Array. However, with the application of good seamanship and given the high minimum spacing between wind turbines (1,000 m), there is not expected to be a visual obstruction to vessels passing at the edge of the Array. It is also noted that most small vessels this far offshore would be expected to be broadcasting on AIS. This assumption aligns with both consultation input (section 13.5), and the vessel traffic survey data collected (section 13.7.1).
  3. The impact will be present throughout the operation and maintenance phase which will last for up to 35 years. Given that third-party vessels are expected to be compliant with Flag State regulations including the COLREGs, the likes of collision avoidance action seek to ensure that the likelihood of an encounter developing into a collision incident is low. This is furthered by the promulgation of information and charting of infrastructure associated with the Array which will increase awareness of the Array and any ongoing major maintenance activities, thus allowing third-party vessels to passage plan in advance (see section 13.10).
  4. The most likely consequences of the impact are as per the equivalent construction phase impact, namely minor contact and damage to property and minor reputational effects on business, but no perceptible effect on people. Although considered less likely, collision between third party vessels  could involve one of the vessels foundering resulting in PLL and the environmental consequence of pollution. Such a scenario would be more likely if one of the thirdparty vessels involved was a small craft and the other a commercial vessel since the small craft may have a weaker structural integrity than the commercial vessel. The Array’s MPCP will be implemented to minimise the environmental effects should pollution occur.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place resulting in the anticipated deviations for the main commercial routes defined for the construction phase being directly applicable for the decommissioning phase. On this basis, the risk of third-party to third-party vessel collision for commercial vessels is considered the same during the decommissioning phase as during the construction phase. However, it is noted that the deviations will be well established by the decommissioning phase, and that vessels will likely be more familiar with the Array than during the construction phase.
  2. The impact will be present throughout the decommissioning phase which is expected to be of similar duration to the construction phase (i.e. maximum of eight years). Given that third-party vessels are expected to be compliant with Flag State regulations including the COLREGs, the likes of collision avoidance action seek to ensure that the likelihood of an encounter developing into a collision incident is low. This is furthered by the promulgation of information and charting of the buoyed decommissioning area which will maximise awareness of ongoing decommissioning activities, thus allowing third-party vessels to passage plan in advance.
  3. The most likely consequences associated with the MDS are as per the equivalent construction phase and operation and maintenance phase impacts.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

Displacement from Adverse Weather Routeing

  1. Some vessels and vessel operators may wish to transit alternative routes during periods of adverse weather. Adverse weather includes wind, wave and tidal conditions as well as reduced visibility due to fog.

                        Construction phase

  1. No specific adverse weather routeing was observed within the baseline vessel traffic data studied, however the long term 12 month AIS analysis within the NRA (volume 3, appendix 13.1) showed a minor weighting towards summer months for cargo vessels, tankers, and oil and gas vessels in terms of traffic volumes. This may indicate that such vessels prefer to pass further inshore of the shipping and navigation study area in adverse conditions (which may be more likely during winter months).
  2. Adverse weather can hinder a vessel’s standard route, its speed of navigation, and/or its ability to enter the destination port. Adverse weather routes are assessed to be significant course adjustments to mitigate vessel motion in adverse weather conditions. When transiting in adverse weather conditions, a vessel is likely to encounter various types of weather and tidal phenomena, which may lead to severe roll motions, potentially causing damage to cargo and equipment, and/or discomfort and danger to persons on board. The sensitivity of a vessel to these phenomena will depend on the actual stability parameters, hull geometry, vessel type, vessel size and speed.
  3. The following key points of relevance to adverse weather were raised during consultation (see section 13.5):
  • Smyril Line stated that vessels would likely not transit through offshore wind farms in adverse weather conditions.
  • It was suggested at the Hazard Workshop that vessels would likely seek to make the most direct safe transit possible during adverse weather.
  • Wilson Ship Management indicated transit choice through the area would depend on weather conditions, and stated preference for passing inshore.
  1. There is open sea area inshore of the site boundary (the closest baseline wind farm is Seagreen 1 Offshore Wind Farm, located 27 nm inshore) and therefore the buoyed construction area is not considered as hindering any preference for inshore routeing.
  2. Details would be promulgated to facilitate advanced passage planning including in adverse conditions. Under COLREGS (IMO, 1972/77), vessels are also required to take appropriate measures with regards to determining a safe speed, taking into account various factors including the state of visibility, the state of the wind, sea, and current as well as the proximity of navigational hazards. In particular, vessels would be able to account for forecast for adverse conditions within their passage planning.
  3. Most likely consequences are minor alterations to existing adverse weather routeing noting the data indicates a preference for inshore routeing in such conditions. As a worst case vessels may be required to pass further offshore than preferred leading to large deviations in adverse conditions and safety concerns.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. As noted in the equivalent construction phase discussion, no specific adverse weather routeing was observed within the baseline vessel traffic data studied, however the long term 12 month AIS analysis within the NRA showed a minor weighting towards summer months for cargo vessels, tankers, and oil and gas vessels in terms of volume.
  2. There is open sea area inshore of the site boundary (the closest operational wind farm is Seagreen 1 Offshore Wind Farm, located 27 nm inshore) and therefore the Array is not considered as hindering any preference for inshore routeing. During the operation and maintenance phase, vessels may be more likely to pass through the Array than during the construction phase, however based on consultation input (see section 13.5) it is unlikely that vessels would choose to transit through the Array during adverse weather conditions.
  3. All infrastructure will be shown on appropriate Admiralty Charts ensuring vessels can passage plan to account for the Array. In particular, vessels would be able to account for forecast for adverse conditions within their passage planning. Under COLREGS (IMO, 1972/77), vessels are also required to take appropriate measures with regards to determining a safe speed, taking into account various factors including the state of visibility, the state of the wind, sea, and current as well as the proximity of navigational hazards.
  4. Most likely consequences are minor alterations to existing adverse weather routeing noting the data indicates a preference for inshore routeing in such conditions. As a worst case vessels may be required to pass further offshore than preferred leading to large deviations in adverse conditions and safety concerns.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is therefore considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place. However, it is noted that the deviations will be well established by the decommissioning phase, and that vessels will likely be more familiar with the Array than during the construction phase.
  2. Details would be promulgated to facilitate advanced passage planning including in adverse conditions. In particular, vessels would be able to account for forecast for adverse conditions within their passage planning. Under COLREGS (IMO, 1972/77), vessels are also required to take appropriate measures with regards to determining a safe speed, taking into account various factors including the state of visibility, the state of the wind, sea, and current as well as the proximity of navigational hazards.
  3. Most likely consequences are minor alterations to existing adverse weather routeing noting the data indicates a preference for inshore routeing in such conditions. As a worst case vessels may be required to pass further offshore than preferred leading to large deviations in adverse conditions and safety concerns.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

Increased Vessel to Vessel Collision Risk (ThirdParty to Project Vessels)

                        Construction phase

  1. Up to 7,902 return trips by construction vessels (and site preparation vessels) may be made throughout the construction phase and will include vessels which are RAM. Project vessels will be managed by marine coordination, including the use of traffic management procedures such as the designation of entry and exit points to and from the buoyed construction area. Project vessels will also carry AIS and be compliant with relevant Flag State regulations, including the COLREGs, and comply with the procedures set out in the NSVMP (which will be a condition of consent).
  2. Safety zones will be applied for including up to 500 m around structures where vessels are undertaking construction work and 50 m around partially completed or completed surface piercing structures prior to commissioning of the wind farm. Such safety zones will protect project vessels involved in construction works which may be RAM. If on-site as deemed necessary via risk assessment, guard vessels will also assist with monitoring safety zones and alerting thirdparty traffic to their presence.
  3. Details of construction activities, including the presence of safety zones and any use of advisory safe passing distances, as defined by risk assessment, will be suitably promulgated to maximise awareness of ongoing construction activities.
  4. Additionally, the use of IALA G1162 (IALA, 2021b) compliant lighting and marking including lights, marks, sounds, signals and other aids to navigation as required by the NLB and the MCA will further maximise awareness, both in day and night conditions including in restricted visibility. An outline LMP is provided in volume 4, appendix 26. This will include details of the buoyed construction area which will be agreed with the NLB and within which project vessels undertaking construction activities will most likely be located during construction activities. As per the impact on vessel displacement, it is anticipated that third-party vessels are unlikely to frequently enter the buoyed construction area and therefore the level of exposure for project vessels located on-site will be very low.
  5. In restricted visibility, there is an increased risk of visual impediment to third-party vessels in relation to identifying project vessels entering and exiting the buoyed construction area. However, the COLREGs regulate vessel movements in adverse weather conditions including the requirement for all vessels operating in reduced visibility to maintain a safe speed which will allow more time for reacting to encounters. COLREGs also covers the movement of project vessels and manages any encounters, and the carriage of AIS by such vessels will also assist with identifying their movements.
  6. It is noted that there will be a need to tow floating substructures out of port during the construction phase. Feedback received at the Hazard Workshop (see section 13.5) was that good seamanship and watchkeeping in compliance with COLREGS were key mitigations. Procedures for vessels towing substructures will also be considered in the VMP. All vessels involved in towing procedures will be lit and marked as required under COLREGS. Precise plans for fabrication and wet storage locations are unknown at this stage. Where enabling works are required within port limits to facilitate fabrication and storage these will be subject to the relevant assessment and licensing for the port works.  Wet storage within the site boundary will be limited.
  7. The impact will be present throughout the construction phase which may last for up to eight years. With the designed in measures noted above implemented, it is considered unlikely that a close encounter between a third-party vessel and a project vessel will occur. In the event that such an encounter does occur, collision avoidance action would be implemented by the vessels as per the COLREGs, thus seeking to ensure that the likelihood of the encounter developing into a collision incident is very low.
  8. From historical incident data, there has been only one collision incident involving a third-party vessel and project vessel in the UK, occurring in a harbour in 2011 and resulting in moderate vessel damage but no harm to any People On Board (POB). No collision incidents have occurred in the period since (in excess of ten years), reflecting the increasing awareness of offshore wind farm developments and improved application of the various measures outlined above.
  9. The most likely consequences in the event of a collision incident between a project vessel and thirdparty vessel are minor contact between the vessels resulting in minor damage to property and minor reputational effects on business but no perceptible effect on people. Although considered less likely collision between third party vessels could involve one of the vessels foundering resulting in PLL and the environmental consequence of pollution. Such a scenario would be more likely if the third-party vessel involved was a small craft which may have weaker structural integrity than a commercial vessel. The Array’s MPCP will be implemented to reduce the environmental effects should pollution occur.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. Up to 508 return trips annually from vessels may be made throughout the operation and maintenance phase and will include vessels which are RAM. As per the construction phase, project vessels will be managed by marine coordination, carry AIS and be compliant with relevant Flag State regulations.
  2. Also, safety zones will be applied for including up to 500 m around structures where vessels are undertaking major maintenance work. Such safety zones will protect project vessels involved in major maintenance which may be RAM. If on-site (determined via risk assessment of major maintenance activities), guard vessels will assist with monitoring safety zones and alerting thirdparty traffic to their presence.
  3. Similarly to the construction phase, details of major maintenance activities including the presence of safety zones and any advisory safe passing distances, as defined by risk assessment, will be suitably promulgated (e.g. via Notice to Mariners, Kingfisher) to maximise awareness of ongoing major maintenance activities.
  4. Additionally, the use of lighting and marking (IALA G1162 compliant (IALA, 2021b)) as required by the NLB and the MCA will further increase awareness, both in day and night conditions including in restricted visibility. In restricted visibility there is an increased risk of visual obstruction to third-party vessels in relation to identifying project vessels entering and exiting the project. However, the COLREGs regulate vessel movements in adverse weather conditions, allowing more time to react to encounters. The carriage of AIS by project vessels will also assist with thirdparty vessels identifying their movements.
  5. As per the equivalent construction phase impact, there has been only one collision incident involving a third-party vessel and project vessel in the UK, occurring in a harbour in 2011 and resulting in moderate vessel damage but no harm to any POB. No collision incidents have occurred in the period since (in excess of ten years), reflecting the increasing awareness of offshore wind farm developments and improved application of the various measures previously outlined.
  6. It is noted that there may be a need to tow floating substructures to/from port during the operation and maintenance phase for maintenance purposes (noting this is only likely to be needed for major component replacement). Feedback received at the Hazard Workshop (see section 13.5) was that good seamanship and watchkeeping in compliance with COLREGS were key mitigations. Procedures for vessels towing substructures will also be considered in the VMP. All vessels involved in towing procedures will be lit and marked as required under COLREGS.
  7. The impact will be present throughout the operation and maintenance phase which may last for up to 35 years. With the designed in measures noted above implemented, it is considered unlikely that an encounter between a third-party vessel and a project vessel will occur. In the event that such an encounter does occur, collision avoidance action would be implemented by the vessels as per COLREGs, thus ensuring that the likelihood of the encounter developing into a collision incident is very low.
  8. The likelihood of an encounter is decreased compared to in the construction phase given that fewer project vessels will generally be on-site at any time.
  9. The most likely consequences in the event of a collision incident between a project vessel and third-party vessel are as per the equivalent construction phase impact, namely minor contact and damage to property and minor reputational effects on business, but no perceptible effect on people. Although considered less likely allision could involve one of the vessels foundering resulting in PLL and the environmental consequence of pollution. Such a scenario would be more likely if the third-party vessel involved was a small craft which may have weaker structural integrity than a commercial vessel. The Array’s MPCP will be implemented to minimise the environmental effects should pollution occur.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
                        Severity of consequence
  1. The severity of consequence is therefore considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the numbers and types of vessel used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, project vessels will be managed by marine coordination, applications will be made for statutory safety zones, and decommissioning activities will generally be located within the buoyed decommissioning area.
  2. The impact will be present throughout the decommissioning phase which is expected to be of similar duration to the construction phase (i.e. maximum of eight years). With the designed in measures previously noted implemented, it is considered unlikely that an encounter between a third-party vessel and a project vessel will occur. As per the equivalent construction phase impact, in the event that such an encounter does occur, collision avoidance action would be implemented by the vessels as per the COLREGs, thus ensuring that the likelihood of the encounter developing into a collision incident is very low.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available searoom, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

Vessel to Structure Allision Risk

  1. The spatial extent of the impact is considered small given that a vessel must be in close proximity to a structure in the Array for an allision incident to occur. The forms of allision considered are:
  • powered allision;
  • drifting allision; and
  • internal allision.
  1. These are discussed separately for each phase, with a combined impact significance ranking provided.

                        Construction phase

                        Powered allision
  1. Powered allision risk may be caused by human/navigational error, unfamiliarity with the Array and/or a failure of an aid to navigation.
  2. Experience from previous under construction offshore wind farms indicates that Masters regularly choose to transit greater than 1 nm from construction works. In doing so, vessels are unlikely to navigate close enough to a structure to create an allision risk. There is a distance of 27 nm between the Array and Seagreen 1 Offshore Wind Farm, the closest baseline offshore wind farm, which provides notable sea room for safe navigation.
  3. Based on the NRA (volume 3, appendix 13.1) modelling, with the main commercial route deviations in place and assuming all structures are installed, the base case annual powered vessel to structure allision frequency is estimated to be 6.91×10-3, corresponding to a return period of approximately one in 145 years.
  4. The impact will be present throughout the construction phase which may last for up to eight years and will cover a greater spatial extent as more structures are installed. Safety zones of up to 50 m around partially completed or completed but not yet fully commissioned surface piercing structures will be in place and assist with ensuring that vessels are aware of the presence of structures. Where identified as necessary via risk assessment (which will include consideration of the other mitigation measures in place), a guard vessel may also be used, which will alert passing vessels to the presence of the ongoing construction activities. Furthermore, the use of lighting and marking as required by the NLB and the MCA (including for partially completed structures), charting of the buoyed construction area and promulgation of information will allow vessels to passage plan a safe route in advance. It should also be noted that commercial vessels are expected to comply with international and Flag State regulations (including the COLREGs and SOLAS). Consultation with the NLB to establish agreement on lighting and marking will be undertaken post-consent. With these designed in measures in place, it is considered unlikely that a powered allision incident will occur.
  5. From historical incident data, there have been no reported instances of a powered allision involving a third-party vessel with a pre-commissioned wind farm structure in the UK.
  6. The most likely consequences in the event of a powered allision incident are minor damage to property with the vessel able to resume passage and undertake a full inspection at the next port. However, this will depend on multiple factors including the energy of the impact, structural integrity of the vessel and the sea state at the time. Given the potential for a non-steel construction, commercial fishing vessels and recreational vessels are considered more vulnerable. Although considered less likely an allision could involve the vessel foundering resulting in PLL and the environmental consequence of pollution. The Array’s MPCP will be implemented to reduce the environmental effects should pollution occur.
                        Drifting allision
  1. Drifting allision risk may be caused by mechanical or technical failure, adverse weather and/or a navigational system error. A vessel adrift may only develop into an allision situation if in proximity to a pre-commissioned structure. This is only the case where the adrift vessel is located in proximity to the buoyed construction area and the wind and/or tide directs the vessel towards a structure.
  2. As discussed in relation to powered allision risk, it is likely that commercial vessels will deviate to avoid the buoyed construction area. As such, it is likely that associated allision risk would be highest to pre-commissioned structures on the periphery of the Array. Smaller vessels may still choose to transit through, and as such may come in proximity to internal structures.
  3. Based on the NRA (volume 3, appendix 13.1) modelling, with the main commercial route deviations in place, the base case annual drifting vessel to structure allision frequency is estimated to be 2.16×10-4, corresponding to a return period of approximately one in 4,619 years.
  4. For drifting allision incidents, the adrift vessel would initiate its emergency response procedures to avoid a Closest Point of Approach (CPA) with a structure resulting in an allision. This may include emergency anchoring following a check of the relevant nautical charts (thus ensuring that the anchor deployment does not lead to other impacts such as anchor snagging on a subsea cable), noting this would depend on the vessel and water depths. These measures may also include the use of thrusters (depending on availability and power supply). Moreover, under SOLAS obligations (IMO, 1974), other nearby vessels including project vessels (via marine coordination) may be able to render assistance, depending on the type and size of vessel.
  5. From historical incident data, there have been no reported instances of a drifting allision involving a third-party vessel with a pre-commissioned wind farm structure in the UK.
  6. Should a drifting allision occur, the consequences will be similar to those noted for the case of a powered allision including the unlikely worst case of foundering and pollution. In the highly unlikely scenario of a drifting allision incident resulting in pollution, the implementation of the MPCP will reduce the environmental risk. Additionally, a drifting vessel is likely to be moving at a reduced speed compared to a powered vessel dependent on conditions, thus reducing the energy of the impact, including in the case of a recreational vessel under sail.
                        Internal allision
  1. As noted in the discussion on third-party vessel to third-party vessel collision risk, it is likely that only smaller vessels (e.g. fishing, recreation) may choose to transit through the Array during construction. On this basis it is considered very unlikely that a commercial vessel would be involved in an internal allision.
  2. Minimum spacing between structures of 1,000 m is considered sufficient for safe internal navigation, i.e. keeping clear of the structures in the Array. The final layout will be agreed with both NLB and MCA, noting these discussions will include consideration of ensuring safe internal navigation.
  3. As with any passage, any vessel navigating in or near the Array is expected to passage plan in accordance with SOLAS Chapter V (IMO, 1974), and promulgation of information will ensure that such vessels have good awareness of the works being undertaken. Charting of the buoyed construction area will further increase mariner awareness.
  4. The Applicant will apply for safety zones of radius 500 m around structures where construction is underway, with 50 m pre-commissioning safety zones applied for around structures where work is not underway during the construction phase. These safety zones would make clear to passing mariners the areas which should be avoided to minimise allision risk.
  5. Should an internal allision occur, the consequences will be similar to those noted in the discussion for the case of a powered allision, including the unlikely worst case of foundering and pollution. In the highly unlikely scenario of an internal allision incident resulting in pollution, the implementation of the MPCP will minimise the environmental risk.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

                        Powered allision
  1. Powered allision risk may be caused by human/navigational error, unfamiliarity with the Array and/or a failure of an aid to navigation.
  2. Experience from previous operational offshore wind farms indicates that Masters regularly choose to transit greater than 1 nm from an array, with it being likely that the deviations established during construction will remain in place during the operation and maintenance phase. In doing so, vessels are unlikely to navigate close enough to a structure to create an allision risk. There is a distance of 27 nm between the Array and the Seagreen 1 Offshore Wind Farm, the closest baseline offshore wind farm, which provides notable sea room for safe navigation.
  3. Based on the NRA (volume 3, appendix 13.1) modelling, with the main commercial route deviations in place, the base case annual powered vessel to structure allision frequency is estimated to be 6.91×10-3, corresponding to a return period of approximately one in 145 years.
  4. The structures will be lit and marked as directed by the MCA and NLB and in compliance with IALA G1162 (IALA, 2021b) to ensure passing mariner awareness (e.g. lights, sound signals, AIS Aids to Navigation (AtoN)). Additionally, commercial vessels are expected to comply with international and Flag State regulations (including the COLREGs and SOLAS) and will be able to passage plan in advance given the promulgation of information relating to the Array, including display of the structure locations on appropriate nautical charts.
  5. NLB raised during consultation (section 13.5) that contingency of overall lighting and marking would need to be considered, in particular in a scenario where a wind turbine with a key AtoN was towed from the Array for maintenance. Appropriate measures for this scenario will be agreed as part of the LMP process.
  6. RYA Scotland raised during consultation that outage of marine lights should be rectified in a timely manner (section 13.5). Associated measures and procedures will be detailed in the outline AtoN Management Plan, outline provided in volume 4, appendix 26, annex A, noting that IALA Availability targets will be set out in the LMP (outline LMP provided in volume 4, appendix 26).
  7. Based on historical incident data as set out in the NRA (volume 3, appendix 13.1), there have been two reported instances of a third-party vessel alliding with an operational wind farm structure in the UK (one in the Irish Sea and one in the Southern North Sea). Both of these incidents involved a fishing vessel, with a RNLI lifeboat attending on both occasions and a helicopter deployed in one case.
  8. The most likely consequences in the event of a powered allision incident are as per the equivalent construction phase impact, namely minor damage to property. Although considered less likely collision between third party vessels  could involve the vessel foundering resulting in PLL and the environmental consequence of pollution. The Array’s MPCP will be implemented to reduce the environmental effects should pollution occur.
                        Drifting allision
  1. Drifting allision risk may be caused by mechanical or technical failure, adverse weather and/or a navigational system error. A vessel adrift may only develop into an allision situation if in proximity to a structure and this is only the case where the adrift vessel is located in proximity to the Array and the wind and/or tide directs the vessel towards a structure.
  2. Based on the NRA (volume 3, appendix 13.1) modelling, with the main commercial route deviations in place, the base case annual drifting vessel to structure allision frequency is estimated to be 2.16×10-4, corresponding to a return period of approximately one in 4,619 years.
  3. For drifting allision incidents, the adrift vessel would initiate its emergency response procedures to avoid a CPA with a structure resulting in an allision. This may include emergency anchoring following a check of the relevant nautical charts (thus ensuring that the anchor deployment does not lead to other impacts such as anchor snagging on a subsea cable), noting this would depend on the vessel and water depths. These measures may also include the use of thrusters (depending on availability and power supply). Moreover, under SOLAS obligations (IMO, 1974), other nearby vessels including project vessels associated with operation and maintenance activities (via marine coordination) may be able to render assistance, depending on the type and size of vessel.
  4. Based on historical incident data as set out in the NRA (volume 3, appendix 13.1), there have been no instances of a third-party vessel alliding with a UK operational wind farm structure whilst Not Under Command (drifting).
  5. The most likely consequences in the event of a drifting allision incident are as per the equivalent construction phase impact, namely minor damage to property. Although considered less likely collision between third party vessels  could involve the vessel foundering resulting in PLL and the environmental consequence of pollution. The Array’s MPCP will be implemented to minimise the environmental effects should pollution occur. The consequences are less likely to be severe for a drifting allision incident given that the speed at which the impact occurs (and subsequent energy of the impact) will generally be dictated by the wind and/or tidal speeds.
                        Internal allision
  1. As per the impact on vessel displacement, it is anticipated that commercial fishing vessels and recreational vessels may choose to navigate internally within the Array, particularly in favourable weather conditions. However, consultation input indicated this may be less likely than within a fixed foundation project. Therefore, an internal allision risk exists for such smaller craft. However, due to the distance offshore of the Array, fishing and recreational vessel traffic volume is expected to be low and this was reflected in the vessel traffic data (section 13.7.1) and input from consultees (section 13.5).
  2. From historical incident data, there has been two reported instances of a third-party vessel alliding with an operational wind farm structure in the UK. Both of these incidents involved a fishing vessel, with a RNLI lifeboat attending on both occasions and a helicopter deployed in one case. Given that the size of the Array and the promulgation of information, there is likely to be a reasonable level of awareness of the Array meaning that such an incident is unlikely to occur at the Array.
  3. The base case annual fishing vessel to structure allision frequency is estimated to be 4.08×10-2, corresponding to a return period of approximately one in 24 years. This is high compared to that estimated for other UK offshore wind farm developments and is reflective of the conservatism of the model, which assumes that fishing vessel activity and volume will not change after installation of the structures. However, it was noted during consultation (see section 13.5) that fishing vessels may be more likely avoid the Array than a fixed foundation offshore wind farm.
  4. Comfort with internal navigation will likely increase throughout the lifetime of the Array and appropriate lighting and marking (agreed with the NLB and MCA, in compliance with IALA G1162 (IALA, 2021b)) will be in place to maximise awareness of the structure locations including internally. The final Array layout will be agreed through the DSLP via consultation with the MCA and NLB, and this will include agreement of a clear identification (ID) marking system on the structures, with each structure clearly displaying its ID visible in all directions, facilitating safe internal navigation. The structure locations will also be displayed on appropriate nautical charts.
  5. The most likely consequences in the event of an allision incident are as per the equivalent construction phase impact, namely minor damage to property. Although considered less likely collision between third party vessels  could involve the vessel foundering resulting in PLL and the environmental consequence of pollution. The Array’s MPCP will be implemented to minimise the environmental effects should pollution occur. The consequences are less likely to be severe for an internal allision incident given that the vessel will be likely transiting at lower speeds whilst in the Array, reducing the severity of impact.
                        Frequency of occurrence
  1. The frequency of occurrence is therefore considered to be extremely unlikely based on the available sea room, outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is therefore considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect, in the absence of mitigation beyond the designed in measures outlined in Table 13.11   Open ▸ , is of tolerable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place and it is anticipated that third-party vessels will be unlikely to enter. Pre-decommissioning or partially removed structures will be similar in nature to pre-commissioning or partially completed structures, and the movement of third-party vessels within and around the buoyed decommissioning area is anticipated to be similar to that within and around the buoyed construction area.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, outputs of the modelling, and consideration of historical incident data.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP which is not significant in EIA terms.

Reduced Access to Local Ports and Harbours

                        Construction phase

  1. The closest port or harbour to the Array is the Port of Aberdeen, located approximately 44 nm to the northwest, on the east coast of Scotland. Given the distance offshore of the Array and the anticipated deviations for the main commercial routes, it is not anticipated that there will be any notable impact on vessel approaches to and from local ports above and beyond the deviations outlined for the vessel displacement impacts associated with the buoyed construction area or the construction activities therein. Regardless, details of construction activities including the presence of safety zones and any advisory safe passing distances, as defined by risk assessment, will be suitably promulgated to increase awareness of ongoing construction activities.
  2. It should be noted that there are also no pilot boarding stations, port authority limits or Vessel Traffic Service (VTS) areas in proximity to the Array given its distance offshore and as such these services will not be impacted.
  3. Up to 7,902 return trips by construction vessels (including site preparation activities) may be made throughout the construction phase and will include vessels which are RAM, noting this will include towing operations. It is not yet known which ports will be used for construction, however, regardless of ports used, all project vessels will be managed by marine coordination, including the use of traffic management procedures. Project vessels will also carry AIS and be compliant with Flag State regulations including the COLREGs. These measures will seek to ensure any impacts on access to ports used are reduced.
  4. The most likely consequences of the impact are increased journey times and distances due to the presence of the buoyed construction area and project vessels, as per the vessel displacement impact. The MDS may include disruption to schedules, but this is considered highly unlikely given the international nature of routeing in the area and the ability to passage plan to reduce timing impacts. No effect is anticipated on port related services such as pilotage.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on the designed in measures in place to manage project vessel movements.
                        Severity of consequence
  1. The severity of consequence is considered to be minor.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be remote. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. As noted for the equivalent construction phase impact, the closest port or harbour to the Array is the Port of Aberdeen. Again, given the distance offshore of the Array and the anticipated deviations for the main commercial routes, it is not anticipated that there will be any notable impact on vessel approaches to and from local ports above and beyond the deviations outlined for the vessel displacement impact. Given the distance offshore, there are also no pilot boarding stations, port authority limits or VTS areas in proximity to the Array. Details of major maintenance activities including the presence of safety zones and any advisory safe passing distances, as defined by risk assessment, will be suitably promulgated to maximise awareness of ongoing operation and maintenance activities.
  2. Up to 508 return trips annually from vessels may be made throughout the operation and maintenance phase and will include vessels which are RAM. It is not yet known which ports will be used; regardless as per the construction phase, project vessels will be managed by marine coordination, carry AIS and be compliant with relevant Flag State regulations. These measures will ensure any impacts on access to ports used are reduced as far as practicable.
  3. The most likely consequences of the impact are as per the equivalent construction phase impact, namely increased journey times and distances. The MDS may include disruption to schedules, but this is considered highly unlikely given the international nature of routeing in the area and the ability to passage plan to reduce timing impacts. No effect is anticipated on port related services such as pilotage.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on the designed in measures in place to manage project vessel movements.
                        Severity of consequence
  1. The severity of consequence is considered to be minor.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be remote. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is and not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, the number of return trips per year by decommissioning vessels will be similar and a buoyed decommissioning area analogous to the buoyed construction area will be in place.
  2. The impact will be present throughout the decommissioning phase which is expected to be of similar duration to the construction phase (i.e. maximum of eight years). Since the anticipated deviations associated with the main commercial routes accessing a local port and the volumes of vessel traffic on such routes are the same as for the equivalent construction phase impact, similar impact is likely.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on the designed in measures in place to manage project vessel movements.
                        Severity of consequence
  1. The severity of consequence is considered to be minor.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be remote. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

Loss of Station

                        Construction phase

  1. The MCA require under their Regulatory Expectations on Moorings for Floating Wind and Marine Devices (MCA and HSE, 2017) that developers arrange TPV of the mooring systems by an independent and competent person/body. The Regulatory Expectations state that TPV is a “continuous activity”, and that if any modifications to a system occur or if new information becomes available with regard to its reliability, additional TPV would be required. This TPV will facilitate management of any risk of failure of the mooring lines.
  2. On this basis, the potential for loss of station is considered unlikely, noting that for a total loss of station, all moorings would be required to fail (based on the MDS there may be up to six mooring lines per foundation). There have been no reports to date of loss of stations from floating UK offshore wind farms.
  3. The Regulatory Expectations also require the provision of continuous monitoring either by Global Positioning System or other suitable means. The Applicant will put such a system in place, with each wind turbine continuously monitored, and with capability of being tracked in the event of a loss of station as detailed in MGN 654 (see designed in measures in Table 13.11   Open ▸ ).
  4. The most likely consequences are failure of a single mooring line leading to a larger excursion zone than typical. As a worst case, total mooring line failure could lead to a drifting platform leading to a collision.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the designed in measures in place in terms of TPV, monitoring and tracking.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. The same designed in measures in terms of TPV and monitoring details for the construction phase will apply during the operation and maintenance phase, based on the requirements of the Regulatory Expectations on Moorings for Floating Wind and Marine Devices (MCA and HSE, 2017) and MGN 654 (MCA, 2021a).
  2. On this basis, the potential for loss of station is considered unlikely, noting that for a total loss of station, all moorings would be required to fail (based on the MDS there may be up to six mooring lines per foundation), and in the event that mooring lines did fail, monitoring and tracking procedures will be in place.
  3. The most likely consequences are failure of a single mooring line leading to a larger excursion zone than typical. As a worst case, total mooring line failure could lead to a drifting platform leading to a collision.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the designed in measures in place such as TPV of project infrastructure, and implementation of a continuous discrete monitoring system.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. The decommissioning phase is considered to be generally analogous to the construction phase in reverse and therefore the likelihood of loss of station during the decommissioning phase is considered to be the same as for the construction phase.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the designed in measures in place in terms of TPV, monitoring and tracking.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

Reduction of UnderKeel Clearance As a Result of Subsea Infrastructure

                        Construction phase

  1. During the construction phase, there may be a need to wet store subsea components including the mooring lines and subsea cables within the Array. During this time, the components would be left on or tethered to the seabed. It is not expected that any components will be an underkeel risk during this period given it is likely that they will be close to the seabed. However, final plans will be confirmed via the CMS which will be approved by MD-LOT in consultation with the MCA and NLB (i.e. it will be confirmed via the CMS that suitable underkeel clearance will be available during the construction phase).
  2. It is noted that the buoyed construction area in place during the construction phase means it is anticipated that third-party vessels will be unlikely to enter on a regular basis based on consultation input and experience of other UK offshore wind farms. This includes the physical marking of the buoys themselves, and the display of the buoyed construction area on appropriate nautical charts.
  3. Should an underwater allision occur, the most likely consequences are minor damage to property and minor reputational effects on business but no perceptible effect on people. Although considered less likely, a more serious interaction could involve the vessel foundering resulting in PLL and the environmental consequence of pollution. The Array’s MPCP will be implemented to reduce the environmental impacts should pollution occur.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on deep water depths within the site boundary.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in Table 13.11   Open ▸ ) is of tolerable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. During the operational phase, vessels navigating in proximity to the floating substructures associated with the Array may be at risk of interaction with either the mooring lines, or any underwater elements of the floating substructures not visible from the surface including the subsea cables. The level of risk will depend on the clearance available above the subsea elements of the substructures (in particular the mooring lines and buoyant sections of dynamic cables).
  2. Up to 681 nm (1,261 km) of inter-array cables and 127 nm (236 km) of interconnector cables may be in place during the operation and maintenance phase. For both the static portion of the inter-array cables and the interconnector cables, with the minimum burial depth anticipated to be 0.4 m, subject to CBRA confirmation. Where cable burial is not possible, external cable protection methods may be deployed which will again be determined within the CBRA. Charted water depths within the site boundary range from 62 m to 84 m below CD and are therefore sufficiently deep that the reduction of underkeel clearance resulting from the presence of cables on the seabed is not of concern to vessel keels.
  3. The inter-array cables may utilise buoyancy modules, which can be used to maintain the lazy-S configuration of the dynamic portion of the inter-array cable to allow extension of the cables in response to the floating foundation movements (see volume 1, chapter 3). The requirement for these buoyancy modules and their final design, including their depth below the waterline, are yet to be confirmed. Final design will be confirmed via the DSLP which will be approved by MD-LOT in consultation with the MCA and NLB (i.e. the DSLP will confirm that the final design of the dynamic cables will maintain suitable underkeel clearances).
  4. Each foundation may utilise up to six mooring lines. There are two substructure types under consideration, namely semi-submersible and Tension Leg Platform (TLP). For semi-submersible substructures, there are three types of mooring configurations: taut, semi-taut and catenary. The NRA (volume 3, appendix 13.1) has considered an example mooring line arrangement based on worst case parameters. On the basis of the example considered, the vessel with the largest draught recorded within the vessel traffic datasets (16.3 m) would need to transit closer than 100 m to the floating wind turbines to risk interaction with the mooring lines. Based on consultation such a passing distance is very unlikely for any third party vessel, particularly for larger vessels. Final design of the mooring lines will be confirmed via the DSLP which will be approved by MD-LOT in consultation with the MCA and NLB (i.e. the DSLP will confirm that the final design of the mooring lines will maintain suitable underkeel clearances).
  5. General consultation input has been that commercial vessels are likely to avoid the Array. This aligns with operational experience of other UK wind farms. Any commercial vessels that does access the Array would be unlikely to transit within close proximity to the floating foundations. Smaller vessels may be more comfortable transiting through the Array, however these will have smaller draughts. It was noted during the Hazard Workshop that fishing vessels up to 24 m would likely keep a clearance of around 250 m to 300 m from the floating foundations, and that larger fishing vessels, such as 70 m to 90 m pelagic vessels, would likely keep a minimum 500 m clearance and would be unlikely to transit through the Array. It was also noted that recreational vessels would likely keep a minimum of 50 m from wind turbines and that even this distance would be unusual, with larger clearance distances typically used.
  6. Details of the infrastructure including the floating foundations, mooring lines and subsea cables will be promulgated to increase awareness of the Array and any potential underkeel interaction risk. The locations of the floating foundations would be clearly shown on appropriate nautical charts, and the locations of the anchors and mooring lines will also be provided to the UKHO for charting purposes.
  7. Should an underwater allision occur, the most likely consequences are minor damage to property and minor reputational effects on business but no perceptible effect on people. Although considered less likely, a more serious interaction could involve the vessel foundering resulting in PLL and the environmental consequence of pollution. The Array’s MPCP will be implemented to reduce the environmental effects should pollution occur.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on deep water depths within the site boundary and the consultation input indicating vessels will not pass in close proximity to the structures.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in Table 13.11   Open ▸ ) is of tolerable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place and it is anticipated that third-party vessels are unlikely to enter on a regular basis.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on deep water depths within the site boundary and the consultation input indicating vessels will not pass in close proximity to the structures.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in Table 13.11   Open ▸ ) is of tolerable significance and ALARP which is not significant in EIA terms.

Anchor Interaction with Subsea Cables (Including Dynamic Cabling)

                        Construction phase

  1. As all cables associated with the Array will be located within the site boundary, anchor interaction with a subsea cables only applies to vessels within the site boundary. However, a buoyed construction area will be in place during the construction phase and it is anticipated that third-party vessels will be unlikely to enter on a regular basis.
  2. It is also considered unlikely that a vessel would drop anchor in the Array unless it was an emergency (e.g. a drifting incident), given water depths are in excess of 60 m. This aligned with the vessel traffic assessment (see section 13.7.1), with no vessels identified as being at anchor over the 12 months assessed in proximity to the Array based on navigational status information broadcast via AIS. In addition, no designated anchorage areas or preferred anchorage locations in proximity to the Array were identified.
  3. Should an anchor interaction incident occur with the cables, the most likely consequences will be low based on historical anchor interaction incidents, with no damage incurred to the cable or the vessel. As an unlikely worst case, a snagging incident could occur and/or the vessel’s anchor and the cable could be damaged. However, with the designed in measures in place including charting and cable burial/protection, this risk will be managed For commercial fishing vessels or recreational vessels the consequences may also include compromised stability of the vessel, however, water depths are such that small vessels are very unlikely to attempt dropping anchor.
  4. As for vessel anchors, there is a risk that fishing gear may interact with any cables. It is the responsibility of fishers to dynamically risk assess whether it is safe to undertake fishing activities within the Array and to make a decision as to whether or not to fish. This decision will be informed by a number of factors, which will include the charted locations of infrastructure within the Array. Further assessment of impacts associated with fishing gear is provided in volume 2, chapter 12.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely given very low frequency of baseline anchoring and the use of cable burial/external cable protection and charting.
                        Severity of consequence
  1. The severity of consequence is considered to be moderate.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be moderate and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in Table 13.11   Open ▸ ) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. During the operation and maintenance phase, vessels may be more likely to enter into the Array following removal of the buoyed construction area, however, consultation input indicated entry may be less frequent than at fixed foundation offshore wind farm developments (see section 13.5).
  2. Scenarios which may lead to a vessel dropping anchor include the following (noting that water depths in the Array are in excess of 60 m, meaning the latter two scenarios are considered particularly unlikely):
  • vessel anchoring in an emergency over subsea cable (e.g. to avoid drifting into a structure, or into an area of busy traffic);
  • vessel dropping anchor inadvertently (e.g. mechanical failure);
  • planned anchoring where vessel is unaware of presence of infrastructure; and
  • vessel dragging anchor over subsea cable following anchor failure.
  1. Due to the distance offshore of the Array and local water depths, anchoring activity is expected to be very limited. This aligned with the vessel traffic assessment (section 13.7.1), with no vessels identified as being at anchor over the 12 months assessed in proximity to the Array based on navigational status information broadcast via AIS. In addition, no designated anchorage areas or preferred anchorage locations in proximity to the Array were identified.
  2. In line with Regulation 34 of SOLAS (IMO, 1974), the charted location of any hazards should be taken into consideration as part of the decision making process of where to anchor. The locations of subsea cables, structure locations and mooring lines will be provided to the UKHO for charting purposes, and as such mariners will be able to include the infrastructure within their decision making processes.
  3. Cable protection will primarily be by seabed burial where possible. The extent and method by which the static portion of the inter-array cables and the interconnector cables will be buried will depend on the results of a detailed seabed survey of the final inter-array and interconnector cable routes and associated CBRA. Where cable burial is not possible, external cable protection methods may be deployed which will again be determined within the CBRA.
  4. It is noted that there will be sections of cables between the seabed and the floating substructures. Interaction with these sections is considered an unlikely event given water depths and the presence of infrastructure means anchoring is unlikely to be attempted in the vicinity of the foundations (outside of an emergency).
  5. Should an anchor interaction incident occur with the cables, the most likely consequences will be low based on historical anchor interaction incidents, with no damage incurred to the cable or the vessel. As an unlikely worst case, a snagging incident could occur and the vessel’s anchor and/or the cable could be damaged. However, with the designed in measures in place, this risk will be managed. For commercial fishing vessels or recreational vessels the consequences may also include compromised stability of the vessel, however, water depths are such that small vessels are very unlikely to attempt dropping anchor.
  6. As for vessel anchors, there is a risk that fishing gear may interact with any cables. It is the responsibility of fishers to dynamically risk assess whether it is safe to undertake fishing activities within the Array and to make a decision as to whether or not to fish. This decision will be informed by a number of factors, which will include the charted locations of infrastructure within the Array (e.g. on UKHO charts, and other electronic charts as appropriate). Further assessment of impacts associated with fishing gear is provided in volume 2, chapter 12.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely given very low frequency of baseline anchoring and the use of cable burial/protection and charting.
                        Severity of consequence
  1. The severity of consequence is considered to be moderate.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be moderate and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place and it is anticipated that third-party vessels will be unlikely to enter on a regular basis.
  2. Static cable sections may be left in situ, noting dynamic cable sections will be removed. Cables left in situ will remain charted and will be located in the site boundary where water depths mean that deliberate anchoring is unlikely.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible given very low frequency of baseline anchoring, the use of cable burial / protection and charting, and increased familiarity with the project post construction.
                        Severity of consequence
  1. The severity of consequence is considered to be moderate.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be moderate and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is and not significant in EIA terms.

Anchor Interaction with Mooring Lines

                        Construction phase

  1. Noting water depths in the vicinity of the site boundary, the visible presence and display on charts of the buoyed construction area and promulgation of information, it is considered unlikely that vessels would attempt to anchor in the vicinity of the mooring lines (which may be wet stored during the construction phase). It is noted that this aligns with the baseline anchoring assessment undertaken on the 12 months of vessel traffic data which did not identify any anchoring activity based on the information broadcast via AIS (see volume 3, appendix 13.1).
  2. As for vessel anchors, there is a risk that fishing gear may interact with any mooring lines. It is the responsibility of fishers to dynamically risk assess whether it is safe to undertake fishing activities within the Array and to make a decision as to whether or not to fish. This decision will be informed by a number of factors, which will include the charted locations of infrastructure within the Array (e.g., on UKHO charts, and other electronic charts as appropriate). Further assessment of impacts associated with fishing gear is provided in volume 2, chapter 12.
  3. There is limited data available with regard to anchor and gear interaction with mooring lines and floating substructures due to lack of precedent of large scale floating wind farms, however, consequences are likely to be similar to that of the cables.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible given very low frequency of baseline anchoring and charting of infrastructure.
                        Severity of consequence
  1. The severity of consequence is considered to be moderate.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be moderate and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. During the operation and maintenance phase, vessels may be more likely to enter into the Array following removal of the buoyed construction area, however consultation input indicates entry may be less frequent than at fixed foundation offshore wind farm developments (see section 13.5).
  2. Noting water depths in the vicinity of the Array, the visible presence of the surface aspects of the floating substructures and display on charts of the infrastructure, it is considered unlikely that vessels would attempt to anchor in the vicinity of the mooring lines.
  3. As for vessel anchors, there is a risk that fishing gear may interact with any mooring lines. It is the responsibility of fishers to dynamically risk assess whether it is safe to undertake fishing activities within the Array and to make a decision as to whether or not to fish. This decision will be informed by a number of factors, which will include the charted locations of infrastructure within the Array (e.g., on UKHO charts, and other electronic charts as appropriate).
  4. As noted during the equivalent construction phase impact, there are limited data available with regards to anchor interaction with mooring lines and floating substructures, however, consequences are likely to be similar to that of the cables.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible given very low frequency of baseline anchoring and charting of infrastructure.
                        Severity of consequence
  1. The severity of consequence is considered to be moderate.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be moderate and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place and it is anticipated that third-party vessels will not enter. It is also noted that it is intended that all mooring lines will be removed as part of the decommissioning process.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible given very low frequency of baseline anchoring and charting of infrastructure.
                        Severity of consequence
  1. The severity of consequence is considered to be moderate.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be moderate and the frequency of occurrence is considered to be negligible. The effect will, therefore, be of broadly acceptable significance, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance and ALARP which is not significant in EIA terms.

Reduction in Search and Rescue Capability

                        Construction phase

  1. The construction phase will lead to an increased level of vessels and personnel in the area over baseline levels. On this basis there may be an increase in the number of incidents requiring emergency response over baseline rates.
  2. Up to 7,902 return trips from construction vessels (including site preparation) may be made throughout the construction phase and will include vessels which are RAM. The presence of project vessels will increase the likelihood of an incident, with the potential to diminish emergency response capability.
  3. Baseline incident rates are considered low in the area based on the data studied, with an average of less than one incident per year indicated within the MAIB, RNLI and helicopter taskings datasets. It is also noted that to date, there have only been 13 reported allision or collision incidents associated with offshore wind farms in the UK as detailed in the NRA (volume 3, appendix 13.1). While it should be considered that this only covers allisions and collisions, it is still not anticipated that the construction phase would notably increase the observed baseline incident rates.
  4. Any on-site project vessels and resources associated with the construction phase will form additional resource to respond to any incidents in the area in liaison with the MCA, both in terms of incidents associated with construction activities (i.e. self-help resources), but also incidents occurring outside of the Array to thirdparty vessels.
  5. As required under MGN 654, the Applicant will produce and submit an ERCoP to the MCA detailing how they would cooperate and assist in the event of an incident including consideration of additional project resources that will be available (e.g. project vessels associated with construction activities). The initial ERCoP will specifically cover the construction phase.
  6. The most likely consequence is a delay caused emergency response request but without notable impact on the operation. As a worst case the delay could lead to PLL.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on consideration of the historical incident data and the designed in measures in place including compliance with MGN 654.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be remote. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP which is not significant in EIA terms.

                        Operation and maintenance phase

  1. The operation and maintenance phase will lead to an increased level of vessels and personnel in the area over baseline levels, however, it is likely to be considerably less than during the construction phase (when more vessels will be present and more activity being undertaken). On this basis there may be an increase in the number of incidents requiring emergency response over baseline rates, albeit likely at lower rates than during the construction phase.
  2. As per the equivalent construction phase discussion, baseline incident rates are considered low in the area, and it is considered unlikely that incident rates will rise notably based on the study of allision and collision incidents that have occurred at other UK offshore wind farms (further details provided in volume 3, appendix 13.1).
  3. Any on-site project vessels and resources associated with the operation and maintenance phase will form additional resource to respond to any incidents in the area in liaison with the MCA, both in terms of incidents associated with the ongoing operation and maintenance activities (i.e. self-help resources), but also incidents occurring outside of the Array to thirdparty vessels.
  4. As required under MGN 654 (MCA, 2021a), the Applicant will produce and submit an ERCoP to the MCA detailing how they would cooperate and assist in the event of an incident including consideration of additional project resources that will be available (e.g. project vessels associated with operation and maintenance activities). The ERCoP will be updated on a regular basis as required by the MCA, and this will include the transfer of the construction phase ERCoP into the operation and maintenance phase ERCoP in advance of the completion of construction. The Applicant will also agree a SAR checklist with the MCA post consent, which will set out the required mitigations of relevance to SAR that will be implemented.
  5. To ensure suitable SAR access is maintained, the final layout of structures will be agreed with the MCA post consent. This will include application of the SAR layout requirements within MGN 654 (MCA, 2021a), noting that there may also be a need for use of Helicopter Refuge Areas given the size of the site boundary. The consideration of MGN 654 in addition to agreement of the layout positions with the MCA will ensure that suitable SAR access is maintained.
  6. The most likely consequence is a delay caused emergency response request but without notable impact on the operation. As a worst case the delay could lead to PLL.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on consideration of the historical incident data and the designed in measures in place including compliance with MGN 654.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be remote. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP which is not significant in EIA terms.

                        Decommissioning phase

  1. Since the methods used to remove infrastructure are expected to be similar to those used for installation, this impact is expected to be similar in nature to the equivalent construction phase impact. In particular, a buoyed decommissioning area analogous to the buoyed construction area will be in place and it is anticipated that third-party vessels would be unlikely to enter on a regular basis.
  2. This also includes the assumption that the vessels on site associated with decommissioning activities will form additional resource to respond to any incidents in the area in liaison with the MCA, both in terms of incidents associated with the decommissioning activities (i.e. self-help resources), but also incidents occurring outside of the Array to thirdparty vessels.
  3. As required under MGN 654 (MCA, 2021a), the Applicant will produce and submit an ERCoP to the MCA detailing how they would cooperate and assist in the event of an incident including consideration of additional project resources that will be available (e.g. project vessels associated with decommissioning). The ERCoP will be updated on a regular basis as required by the MCA, and this will include an update prior to decommissioning.
  4. The most likely consequence is a delay caused emergency response request but without notable impact on the operation. As a worst case the delay could lead to PLL.
                        Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on consideration of the historical incident data and the designed in measures in place including compliance with MGN 654.
                        Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be remote. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
                        Secondary mitigation and residual effect
  1. No secondary shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP which is not significant in EIA terms.

13.12.            Cumulative Effects Assessment

13.12. Cumulative Effects Assessment

13.12.1.         Methodology

13.12.1. Methodology

  1. The Cumulative Effects Assessment (CEA) assesses the impact associated with the Array together with other relevant plans, projects and activities. Cumulative effects are defined as the combined effect of the Array in combination with the effects from a number of different projects, on the same receptor or resource. Further details on CEA methodology are provided in volume 1, chapter 6.
  2. The projects and plans selected as relevant to the CEA presented within this chapter are based upon the results of a screening exercise (see volume 3, appendix 6.4 of the Array EIA Report). Volume 3, appendix 6.4 further provides information regarding how information pertaining to other plans and projects is gained and applied to the assessment. Each project or plan has been considered on a case-by-case basis for screening in or out of this chapter's assessment based upon data confidence, impact-receptor pathways and the spatial/temporal scales involved.
  3. In undertaking the CEA for the Array, it should be noted that other projects and plans under consideration will have differing potential for proceeding to an operational stage and hence a differing potential to ultimately contribute to a cumulative impact alongside the Array. Therefore, a tiered approach has be adopted which provides a framework for placing relative weight upon the potential for each project/plan to be included in the CEA to ultimately be realised, based upon the project/plan’s current stage of maturity and certainty in the projects’ parameters. The tiered approach which will be utilised within the overarching Array CEA employs the following tiers:
  • tier 1 assessment – Array and Proposed offshore export cable corridor(s) and Proposed onshore transmission infrastructure and all plans/projects which became operational since baseline characterisation, those under construction and those with consent and submitted but not yet determined;
  • tier 2 assessment – All plans/projects assessed under Tier 1, plus those projects with a Scoping Report; and
  • tier 3 assessment – All plans/projects assessed under Tier 2, which are reasonably foreseeable, plus those projects likely to come forward where an Agreement for Lease (AfL) has been granted.
  1. It is noted that the cumulative routeing assessment in the NRA uses its own tiering system based on development status, distance from the Array, level of interaction with baseline traffic of relevance to the Array, level of concern raised during consultation, and data confidence. Full details are provided in the NRA (volume 3, appendix 13.1). This chapter considers the cumulative routeing outputs, but applies the tiering shown in Table 13.12   Open ▸ . The NRA also considers a 50 nm buffer for cumulative routeing.
  2. The specific projects scoped into the CEA for shipping and navigation for the purposes of the Array EIA Report chapter are outlined in Table 13.12   Open ▸ .
  3. The range of potential cumulative impacts that are identified and included in Table 13.13   Open ▸ , is a subset of those considered for the Array alone CEA assessment. This is because some of the potential impacts identified and assessed for the Array alone, are localised and temporary in nature. It is considered therefore, that these potential impacts have limited or no potential to interact with similar changes associated with other plans or projects. These have therefore not been taken forward for detailed assessment. The scoped out impacts are:
  • loss of station;
  •  reduction of under keel clearance as a result of subsea infrastructure;
  • anchor interaction with subsea cables (including dynamic cabling); and
  • anchor interaction with mooring lines.
  1. Similarly, some of the potential impacts considered within the Array alone assessment are specific to a particular phase of development (e.g. construction, operation and maintenance or decommissioning). Where the potential for cumulative effects with other plans or projects only have potential to occur where there is spatial or temporal overlap with the Array during certain phases of development, impacts associated with a certain phase may be omitted from further consideration where no plans or projects have been identified that have the potential for cumulative effects during this period.
  2. It should be noted that there are no impact pathways in respect of the Proposed onshore transmission infrastructure that could result in a cumulative impact on shipping and navigation receptors scoped into the CEA. Therefore, the Proposed onshore transmission infrastructure has not been considered further within this CEA.

Figure 13.5:
Other Projects/Plans Screened into the CEA for Shipping and Navigation

Figure 13.5: Other Projects/Plans Screened into the CEA for Shipping and Navigation

 

Table 13.12:
List of Other Projects and Plans Considered within the CEA for Shipping and Navigation

Table 13.12: List of Other Projects and Plans Considered within the CEA for Shipping and Navigation

 

13.12.2.         Maximum Design Scenario

13.12.2. Maximum Design Scenario

  1. The MDSs identified in Table 13.13   Open ▸ have been selected as those having the potential to result in the greatest effect on an identified receptor or receptor group. The cumulative effects presented and assessed in this section have been selected from the details provided in volume 1, chapter 3 of the Array EIA Report as well as the information available on other projects and plans (see volume 3, appendix 6.4), to inform an MDS. Effects of greater significance are not predicted to arise should any other development scenario, based on details within the Project Description (volume 1, chapter 3) (e.g. different wind turbine layout), to that assessed here, be taken forward in the final design scheme.

 

Table 13.13:
Maximum Design Scenario Considered for Each Impact as part of the Assessment of Likely Significant Cumulative Effects on Shipping and Navigation

Table 13.13: Maximum Design Scenario Considered for Each Impact as part of the Assessment of Likely Significant Cumulative Effects on Shipping and Navigation

13.12.3.         Cumulative Effects Assessment

13.12.3. Cumulative Effects Assessment

  1. An assessment of the likely significance of the cumulative effects of the Array upon shipping and navigation receptors arising from each identified impact is given below.

Increased vessel to vessel collision risk resulting from displacement (thirdparty to thirdparty)

                        Tier 1

                        Construction phase
  1. Any displacement associated with the installation of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the installation vessel activities and temporary in nature. Details of the installation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning.
  2. Based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1), it is not anticipated that Inch Cape Offshore Wind Farm, Berwick Bank Offshore Wind Farm, or the Seagreen 1A Project will impact main routes also interacting with the Array. As such, deviations on a cumulative basis are likely to be similar to the deviations assuming only the buoyed construction area is in place.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room around Tier 1 developments and the temporary nature of the cable installation impact.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. Any displacement associated with the offshore export cable(s) required for the Array during the operation and maintenance phase will be limited to any maintenance activity requiring the presence of a vessel. This displacement would be spatially limited to the area immediately around the vessel activities and temporary in nature. Details of the operation would be promulgated in advance via the usual means including Notices to Mariners and Kingfisher bulletins ensuring awareness will be maximised, and facilitating passage planning.
  2. As for the construction phase, it is not anticipated that Inch Cape Offshore Wind Farm, Berwick Bank Offshore Wind Farm or the Seagreen 1A Project will impact main routes also interacting with the Array, as per the cumulative routeing assessment in the NRA (volume 3, appendix 13.1). As such, deviations on a cumulative basis are likely to be similar to the deviations assuming the Array alone case.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room around Tier 1 developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Decommissioning phase
  1. Any displacement associated with the decommissioning of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the associated vessel activities and temporary in nature. Details of the decommissioning would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning.
  2. As for the construction and operation and maintenance phases, it is not anticipated that Inch Cape Offshore Wind Farm, Berwick Bank Offshore Wind Farm or the Seagreen 1A Project will impact main routes also interacting with the Array, as per the cumulative routeing assessment in the NRA (volume 3, appendix 13.1).
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room around Tier 1 developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

                        Tier 2

                        All phases
  1. Based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1), it is anticipated that the majority of vessels will choose to pass inshore of the Array, between Seagreen 1 Offshore Wind Farm (screened out as part of the baseline) and Morven Offshore Wind Farm on the basis that:
  • Consultation input including at the Hazard Workshop indicates that commercial vessels are likely to prefer to pass in open sea room rather than between or in proximity to wind farm arrays.
  • The open sea room means that vessels will be able to passage plan with minimal waypoints on their transits.
  • Overall percentage increases in deviations associated with this routeing option are low are low when compared to the route lengths as a whole (the busiest route [Route 2] is approximately 700 nm in total length, with the inshore deviation leading to an estimated increase of less than 1%).
  1. There is in excess of 10 nm of navigable sea area between Seagreen 1 Offshore Wind Farm and Morven Offshore Wind Farm, and therefore there is considered to be sufficient sea space to accommodate any additional transits form vessels choosing to deviate through this inshore area.
  2. Some vessels may also choose to pass offshore of the Array, noting that the presence of Salamander Offshore Wind Farm and Muir Mhor Offshore Wind Farm to the north may mean this will lead to a larger deviation than passing inshore.
  3. The Cenos Offshore Wind Farm is located approximately 50 nm from the Array, and is unlikely to contribute notably to cumulative deviations to the routes also interacting with the Array, other than for oil and gas vessels from Montrose. These vessels will be able to pass either north or south of the Cenos Offshore Wind Farm, or through at the master’s discretion.
  4. The proximity of the Morven Offshore Wind Farm means that lighting and marking and also charting will need to be considered cumulatively. This will ensure vessels are aware of the projects and are able to passage plan accordingly.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. Assuming consultation with the MCA and NLB on the cumulative lighting and marking and charting of the Array and other Tier 2 developments, the effect is considered to be of tolerable significance and ALARP, which is not significant in EIA terms.

                        Tier 3

                        All phases
  1. Based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1) which considers all Tier 3 developments, it is anticipated that the majority of vessels will choose to pass inshore of the Array, between Seagreen 1 Offshore Wind Farm (screened out as part of the baseline) and Morven Offshore Wind Farm (Tier 2) as described in the equivalent Tier 2 assessment. The inclusion of other Tier 3 developments is considered as making it more likely that vessels will choose to pass inshore of the Array given the generally offshore locations of the other proposed Tier 3 arrays, in particular the location of the Bowdun Offshore Wind Farm. The addition of Tier 3 developments does not reduce the available sea room between Seagreen 1 Offshore Wind Farm and Morven Offshore Wind Farm. Further north, the Flora Floating Offshore Wind Farm may mean that vessels are more likely to pass inshore of the Hywind Offshore Wind Farm (screened out as part of the baseline), however passing between the Flora Floating Offshore Wind Farm and the Muir Mhor Offshore Wind Farm will also be an option.
  2. Vessels choosing to pass further offshore may use the sea area between the Array and Bellrock Offshore Wind Farm, noting that general consensus during consultation including the hazard workshop was that there was sufficient sea space to accommodate likely users. There is also the option to pass further offshore, between the Campion Offshore Wind Farm and Bellrock Offshore Wind Farm. Any vessels choosing such passage would need to pass either north or south of the Cedar array.
  3. The location of the Aspen array is considered as being unlikely to significantly contribute to cumulative deviations, given that as discussed above most vessels on north/south are likely to pass inshore. 
  4. In addition to the Morven Offshore Wind Farm (Tier 2), the proximity of the Bellrock Offshore Wind Farm means that lighting and marking and also charting will need to be considered cumulatively. This will ensure vessels are aware of the projects and are able to passage plan accordingly.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. Assuming consultation with the MCA and NLB on the cumulative lighting and marking and charting of the Array and other Tier 2 and Tier 3 developments, the effect is considered to be of tolerable significance and ALARP, which is not significant in EIA terms.

Displacement from adverse weather routeing

                        Tier 1

                        Construction phase
  1. Any displacement associated with the installation of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the installation vessel activities and temporary in nature. Details of the installation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning. As such no notable cumulative impact on adverse weather routeing is anticipated.
  2. Based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1), it is not anticipated that the Inch Cape Offshore Wind Farm, Berwick Bank Offshore Wind Farm or the Seagreen 1A Project will impact main routes also interacting with the Array, and therefore only irregular transits are likely to be impacted. There is in excess of 30 nm between the Array and the Tier 1 projects, facilitating inshore routeing to the west of the buoyed construction area if this is vessel preference during adverse conditions.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room and the temporary nature of cable installation.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. Any displacement associated with the offshore export cable(s) required for the Array during the operation and maintenance phase will be limited to any maintenance activity requiring the presence of a vessel. This displacement would be spatially limited to the area immediately around the vessel activities and temporary in nature. Details of the operation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning. As such no notable cumulative impact on adverse weather routeing is anticipated.
  2. As noted for the construction phase, when accounting for the presence of the Inch Cape Offshore Wind Farm, the Berwick Bank Offshore Wind Farm and the Seagreen 1A Project there is sea room available inshore of the Array to accommodate inshore routeing if this is vessel preference during adverse weather conditions (there is in excess of 30 nm between the Array and the Tier 1).
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room around Tier 1 developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
                        Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Decommissioning phase
  1. Any displacement associated with the decommissioning of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the associated vessel activities and temporary in nature. Details of the decommissioning would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning.
  2. As for the construction and operation and maintenance phases, when accounting for the presence of the Inch Cape Offshore Wind Farm, Berwick Bank Offshore Wind Farm and the Seagreen 1A Project there is considered to be sea room available to allow for any inshore routeing preference during adverse weather (there is in excess of 30 nm between the Array and the closest Tier 1 project).
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room around Tier 1 developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

                        Tier 2

                        All phases
  1. There is in excess of 10nm of navigable sea area between Seagreen 1 Offshore Wind Farm (screened out as part of the baseline) and Morven Offshore Wind Farm, and therefore there is considered to be sufficient sea room to accommodate any additional transits from vessels choosing an inshore passage as a result of adverse weather. It is considered likely based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1), that most vessels will choose this routeing option for deviation, passing inshore of both the Morven Offshore Wind Farm and the Salamander Offshore Wind Farm. There is open sea room to the east for any vessels choosing to pass further offshore, with other Tier 2 developments in excess of 25nm from the Array.
  2. The proximity of the Morven Offshore Wind Farm means that lighting and marking and also charting will need to be considered cumulatively. This will ensure vessels are aware of the projects and are able to passage plan accordingly including during adverse weather.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. Assuming consultation with the MCA and NLB on the cumulative lighting and marking and charting of the Array and other Tier 2 developments, the effect is considered to be of tolerable significance and ALARP, which is not significant in EIA terms.

                        Tier 3

                        All phases
  1. The inclusion of Tier 3 developments is considered as increasing the likelihood that vessels will pass inshore (including during adverse weather), noting that no Tier 3 developments result in reduced sea room between Seagreen 1 Offshore Wind Farm (screened out as part of the baseline) and Morven Offshore Wind Farm (Tier 2). Any vessels choosing to pass further offshore will likely use either the sea space between the Array and Bellrock Offshore Wind Farm, or between Campion Offshore Wind Farm and Bellrock Offshore Wind Farm. Any vessels choosing such passage would need to pass either north or south of the Cedar array.
  2. The location of the Aspen array is considered as being unlikely to significantly contribute to cumulative deviations, given that as discussed above most vessels on north/south are likely to pass inshore, including during adverse weather. 
  3. In addition to the Morven Offshore Wind Farm (Tier 2), the proximity of the Bellrock Offshore Wind Farm means that lighting and marking and also charting will need to be considered cumulatively. This will ensure vessels are aware of the projects and are able to passage plan accordingly including during adverse weather.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, the outputs of the modelling, and consideration of historical incident data.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. Assuming consultation with the MCA and NLB on the cumulative lighting and marking and charting of the Array and other Tier 2 and Tier 3 developments, the effect is considered to be of tolerable significance and ALARP, which is not significant in EIA terms.

Increased vessel to vessel collision risk (thirdparty to Array vessels)

                        Tier 1

                        Construction phase
  1. Any collision risk associated with the installation of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the installation vessel activities and temporary in nature. Details of the installation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be increased and facilitating passage planning, thus reducing any collision risk associated with the installation. Any encounters that did occur between a thirdparty vessel and the cable installation vessel would be managed via COLREGS.
  2. It is anticipated that Inch Cape Offshore Wind Farm and the Seagreen 1A Project will be operational prior to commencement of construction of the Array. Timelines are less certain for Berwick Bank Offshore Wind Farm, however based on current understanding of timelines there is unlikely to be a large overlap between the end of the Berwick Bank Offshore Wind Farm construction and construction of the Array. Therefore, it is likely that the only additional project vessels on a cumulative basis will be those associated with the operation and maintenance of Tier 1 projects (i.e. likely less than during the construction phases), up until decommissioning.
  3. Inch Cape Offshore Wind Farm is likely to be utilising similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are conditions of the Inch Cape Offshore Wind Farm consent, and that all vessels associated with Inch Cape Offshore Wind Farm will be required to comply with COLREGS and SOLAS. The same applies for the Seagreen 1A Project. It is likely that similar procedures will be implemented by Berwick Bank Offshore Wind Farm, noting that the implementation of a VMP and NSP is a standard condition of consent.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. Any collision risk associated with the offshore export cable(s) required for the Array during the operation and maintenance phase will be limited to any maintenance activity requiring the presence of a surface vessel. This risk would be spatially limited to the area immediately around the vessel activities and temporary in nature. Details of the operation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be increased and facilitating passage planning, and thus reduce collision risk.
  2. As for the construction phase impact, the Inch Cape Offshore Wind, Seagreen 1A Project and the Berwick Bank Offshore Wind Farm are likely to be implementing similar vessel management procedures and mitigations as will be the case for the Array (e.g. VMP, NSP, safety zones).
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Decommissioning phase
  1. Any collision risk associated with the decommissioning of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the associated vessel activities and temporary in nature. Details of the decommissioning would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning, thus minimising collision risk.
  2. As for the construction phase and operation and maintenance phase impacts, the Inch Cape Offshore Wind, the Seagreen 1A Project and the Berwick Bank Offshore Wind Farm are likely to be implementing similar vessel management procedures and mitigations as will be the case for the Array (e.g. VMP, NSP, safety zones).
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

                        Tier 2

                        Construction phase
  1. All Tier 2 projects are anticipated to implement similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are standard conditions of consent, and that all vessels associated with Tier 2 projects will be required to comply with COLREGS and SOLAS.
  2. During the construction phase, there will be elevated levels of vessels on site and in the general area (noting ports are still to be decided). There may be overlap between the construction phase, and the construction phases of other Tier 2 developments. Ports to be used for other developments are also unknown, however, as above vessel movements will all be managed.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. During the operation and maintenance phase, all Tier 2 projects are anticipated to implement similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are standard conditions of consent, and that all vessels associated with Tier 2 projects will be required to comply with COLREGS and SOLAS.
  2. During the operation and maintenance phase, there are likely to be lower levels of vessels on site and in the general area, noting ports are still to be decided. Ports to be used for other developments are also unknown, however, as above vessel movements will all be managed.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.
                        Decommissioning phase
  1. During the decommissioning phase, all Tier 2 projects are anticipated to implement similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are standard conditions of consent (outlines provided in volume 4, appendix 26), and that all vessels associated with Tier 2 projects will be required to comply with COLREGS and SOLAS.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.

                        Tier 3

                        Construction phase
  1. All Tier 3 projects are anticipated to implement similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are standard conditions of consent, and that all vessels associated with Tier 3 projects will be required to comply with COLREGS and SOLAS.
  2. During the construction phase, there will be elevated levels of vessels on site and in the general area (noting ports are still to be decided). There may be overlap between the construction phase, and the construction phases of other Tier 3 developments. Ports to be used for other developments are also unknown, however, as above vessel movements will all be managed.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. During the operation and maintenance phase, all Tier 3 projects are anticipated to implement similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are standard conditions of consent and that all vessels associated with Tier 3 projects will be required to comply with COLREGS and SOLAS.
  2. During the operation and maintenance phase, there are likely to be lower levels of vessels on site and in the general area, noting ports are still to be decided. Ports to be used for other developments are also unknown, however, as above vessel movements will all be managed.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.
                        Decommissioning phase
  1. During the decommissioning phase, all Tier 3 projects are anticipated to implement similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination and use of safety zones. It is also noted that the production of a VMP and NSP are standard conditions of consent, and that all vessels associated with Tier 3 projects will be required to comply with COLREGS and SOLAS.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, consideration of historical incident data, and the designed in measures in place to manage project vessel movements and activities.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.

Vessel to structure allision risk

                        Tier 1

  1. There will be no allision impact associated with the offshore export cable(s) required for the Array during any phase.
                        Construction phase
  1. It is anticipated that Inch Cape Offshore Wind Farm will be operational prior to commencement of construction of the Array, with this also likely being the case for Berwick Bank Offshore Wind Farm noting timelines are less certain. Both would therefore have operational mitigations active, in particular lighting and marking in agreement with NLB (a LMP is a condition of the Inch Cape Offshore Wind Farm consent and is a standard condition).
  2. Other Tier 1 offshore wind developments are in excess of 30 nm from the Array, and therefore given the localised nature of allision risk, any notable additional cumulative risk is unlikely, noting that the NRA cumulative routeing assessment (volume 3, appendix 13.1) indicated likely limited interaction with Inch Cape Offshore Wind Farm and Berwick Bank Offshore Wind Farm to vessels also passing the Array.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the distance to other Tier 1 offshore wind developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. It is anticipated that Inch Cape Offshore Wind Farm will be operational prior to commencement of construction of the Array, with this also likely being the case for Berwick Bank Offshore Wind Farm noting timelines are less certain. During the operation and maintenance phase, both will therefore likely have operational mitigations active, in particular lighting and marking in agreement with NLB (a LMP is a condition of the Inch Cape Offshore Wind Farm consent and is a standard condition).
  2. Other Tier 1 offshore wind developments are in excess of 30 nm from the Array, and therefore given the localised nature of allision risk, any notable additional cumulative risk is unlikely, noting that the NRA cumulative routeing assessment (volume 3, appendix 13.1) indicated likely limited interaction with Inch Cape Offshore Wind Farm and Berwick Bank Offshore Wind Farm to vessels also passing the Array.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the distance to other Tier 1 offshore wind developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Decommissioning phase
  1. Decommissioning timelines of Inch Cape Offshore Wind Farm Seagreen 1A Project, and Berwick Bank Offshore Wind Farm are unknown, however given they are anticipated to be operational prior to commencement of construction of the Array, they may be decommissioned in advance of decommissioning of the Array. These projects are likely to utilise industry standard mitigations during decommissioning, including use of a buoyed decommissioning area and temporary lighting where appropriate.
  2. Other Tier 1 offshore wind developments are in excess of 30 nm from the Array, and therefore given the localised nature of allision risk, any notable additional cumulative risk is unlikely, noting that the NRA cumulative routeing assessment (volume 3, appendix 13.1) indicated likely limited interaction with Inch Cape Offshore Wind Farm and Berwick Bank Offshore Wind Farm to vessels also passing the Array.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible based on the distance to other Tier 1 offshore wind developments.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

                        Tier 2

                        All phases
  1. As discussed within the cumulative displacement impact commentary, based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1) it is likely that most vessels currently transiting within or near the Array will choose to pass inshore between Seagreen 1 Offshore Wind Farm (screened out as part of the baseline) and Morven Offshore Wind Farm, where there is in excess of 10 nm of width of sea room available for transit (which is considered sufficient to safely accommodate additional vessel transits without unduly increasing allision risk given allision risk is localised to each development). Vessels choosing to pass further have open sea room to the east.
  2. All Tier 2 developments will be required to agree lighting and marking with the NLB to ensure navigational safety including managing allision risk. Similarly, layouts must also be agreed with the MCA and NLB, with these discussions including consideration of internal allision risk. The proximity of the Morven Offshore Wind Farm means that lighting and marking and also charting will need to be considered cumulatively. This will ensure vessels are aware of the projects and are able to passage plan accordingly to manage cumulative allision risk.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, outputs of the modelling, and consideration of historical incident data.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA.
Further mitigation and residual effect
  1. Assuming consultation with the MCA and NLB on the cumulative lighting and marking and charting of the Array and other Tier 2 developments, the effect is considered to be of tolerable significance and ALARP, which is not significant in EIA terms.

                        Tier 3

                        All phases
  1. The inclusion of Tier 3 developments is considered as increasing the likelihood that vessels will pass inshore in particular the Bowdun Offshore Wind Farm and the Flora Floating Wind Farm, noting that no Tier 3 developments result in reduced sea room between Seagreen 1 Offshore Wind Farm (screened out as part of the baseline) and Morven Offshore Wind Farm (Tier 2). Tier 3 developments do not reduce this available sea space, where there is in excess of 10 nm of width of sea room available for transit which is considered sufficient to safely accommodate additional vessel transits without unduly increasing allision risk. This includes the Aspen and Cedar projects which are both located in excess of 25 nm from the Array.
  2. Any vessels choosing to pass further offshore will likely use either the sea space between the Array and Bellrock Offshore Wind Farm, or between Campion Offshore Wind Farm and Bellrock Offshore Wind Farm. There is in excess of 10 nm of sea room between Campion Offshore Wind Farm and Bellrock Offshore Wind Farm, and consensus during consultation including at the Hazard Workshop was that the space available between Bellrock Offshore Wind Farm and the Array was also sufficient to manage any associated risk.
  3. In addition to Tier 2 developments, all Tier 3 developments will be required to agree lighting and marking with the NLB to ensure navigational safety including managing allision risk. Similarly, layouts must also be agreed with the MCA and NLB, with these discussions including consideration of internal allision risk. In addition to the Morven Offshore Wind Farm (Tier 2), the proximity of the Bellrock Offshore Wind Farm means that lighting and marking and also charting will need to be considered cumulatively.
Frequency of occurrence
  1. The frequency of occurrence is considered to be extremely unlikely based on the available sea room, outputs of the modelling, and consideration of historical incident data.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be extremely unlikely. The effect will, therefore, be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. Assuming consultation with the MCA and NLB on the cumulative lighting and marking and charting of the Array and other Tier 2 and Tier 3 developments, the effect is considered to be of tolerable significance and ALARP, which is not significant in EIA terms.

Reduced access to local ports and harbours

                        Tier 1

                        Construction phase
  1. Any displacement associated with the installation of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the installation vessel activities and temporary in nature. Details of the installation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be increased and facilitating passage planning. Any cumulative impact on port access is therefore unlikely.
  2. It is anticipated that Inch Cape Offshore Wind Farm and the Seagreen 1A Project will be operational prior to commencement of construction of the Array, with this also likely being the case for Berwick Bank Offshore Wind Farm noting timelines are less certain. Therefore, it is likely that the only additional project vessels on a cumulative basis will be those associated with the operation and maintenance of Tier 1 projects, meaning it is likely that traffic volumes will be lower than during their respective construction phases, up until decommissioning.
  3. These projects are likely to be utilising similar vessel management mitigations to those discussed in section 13.10, in particular marine coordination. It is also noted that the production of a VMP and NSP are conditions of the Inch Cape Offshore Wind Farm consent and are standard conditions. These measures will seek to ensure vessel movements including in and out of port are managed.
  4. Given the distance between the Tier 1 offshore wind developments and the Array (all in excess of 30 nm), there will be no direct impact on port access from the associated structures outside of the deviations which have already been assessed separately. Based on the cumulative routeing assessment in the NRA (volume 3, appendix 13.1), it is not anticipated that the Inch Cape Offshore Wind Farm, Seagreen 1A Project or Berwick Bank Offshore Wind Farm will impact main routes also interacting with the Array.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible considering the extent of the cumulative study area and based on the available sea room around Tier 1 developments and the temporary nature of the cable installation impact.
Severity of consequence
  1. The severity of consequence is considered to be minor.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Operation and maintenance phase
  1. Any displacement associated with the offshore export cable(s) required for the Array during the operation and maintenance phase will be limited to any maintenance activity requiring the presence of a vessel. This displacement would be spatially limited to the area immediately around the vessel activities and temporary in nature. Details of the operation would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins seeking to ensure awareness will be increased and facilitating passage planning. Any cumulative impact on port access is therefore unlikely.
  2. As noted in the construction phase impact, it is anticipated that the Inch Cape Offshore Wind Farm and the Seagreen 1A Project will be operational prior to commencement of construction of the Array, with this also likely being the case for the Berwick Bank Offshore Wind Farm noting timelines are less certain. Therefore, during the operation and maintenance phase for the Array, it is likely that the only additional project vessels on a cumulative basis will be those associated with the operation and maintenance of the Tier 1 projects, meaning it is likely that traffic volumes associated with the Tier 1 projects will be lower than during the construction phases, up until decommissioning.
  3. These projects are likely to be utilising similar vessel management mitigations to those discussed in section 13.10 during the operation and maintenance phase, in particular marine coordination. It is also noted that the production of a VMP and NSP are conditions of the Inch Cape Offshore Wind Farm consent and are standard conditions. These measures will ensure vessel movements including in and out of port are managed.
  4. Given the distance between the Tier 1 offshore wind developments and the Array (in excess of 30 nm) there will be no direct impact on port access from the associated structures outside of the deviations which have already been assessed separately. Based on the cumulative routeing assessment in the NRA, it is not anticipated that the Inch Cape Offshore Wind Farm, Seagreen 1A Project or Berwick Bank Offshore Wind Farm will impact main routes also interacting with the Array.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible considering the extent of the cumulative study area and based on the available sea room around Tier 1 developments and the temporary nature of the cable installation impact.
Severity of consequence
  1. The severity of consequence is considered to be minor.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.
                        Decommissioning phase
  1. Any displacement associated with the decommissioning of the offshore export cable(s) required for the Array will be spatially limited to the area immediately around the associated vessel activities and temporary in nature. Details of the decommissioning would be promulgated in advance via the usual means including Notice to Mariners and Kingfisher bulletins ensuring awareness will be maximised and facilitating passage planning.
  2. Cumulative impacts on port access from the Inch Cape Offshore Wind Farm, Seagreen 1A Project and the Berwick Bank Offshore Wind Farm are considered equivalent to the corresponding construction phase impact.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible considering the extent of the cumulative study area and based on the available sea room around Tier 1 developments and the temporary nature of the cable installation impact.
Severity of consequence
  1. The severity of consequence is considered to be minor.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

                        Tier 2

                        All phases
  1. Given the distance offshore of Tier 2 developments, there is unlikely to be any direct impact on port access from the structures outside of the cumulative deviations that have already been assessed.
  2. All Tier 2 developments are likely to be utilising similar vessel management mitigations to those deployed fort the Array, in particular marine coordination. It is also noted that the production of a VMP and NSP are standard conditions of consent. These measures will seek to ensure vessel movements including in and out of port are managed.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible considering the extent of the cumulative study area and based on the available sea room.
Severity of consequence
  1. The severity of consequence is considered to be minor.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

                        Tier 3

                        All phases
  1. Given the distance offshore of Tier 3 developments, there is unlikely to be any direct impact on port access from the structures outside of the cumulative deviations that have already been assessed.
  2. As for Tier 2, all Tier 3 developments are likely to be utilising similar vessel management mitigations to those deployed fort the Array, in particular marine coordination. It is also noted that the production of a VMP and NSP are standard conditions of consent. These measures will seek to ensure vessel movements including in and out of port are managed.
Frequency of occurrence
  1. The frequency of occurrence is considered to be negligible considering the extent of the cumulative study area and based on the available sea room.
Severity of consequence
  1. The severity of consequence is considered to be minor.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be minor and the frequency of occurrence is considered to be negligible. The effect will therefore be of broadly acceptable significance, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of broadly acceptable significance, which is not significant in EIA terms.

Reduction in SAR Capability

                        Tier 1

                        All phases
  1. Given the low baseline incident rates, there is not considered likely to be a notable effect on emergency response resources on a cumulative level. This takes account of historical data showing that allisions and collisions caused by offshore wind farms do not occur at a high frequency (as detailed in the NRA (volume 3, appendix 13.1)), in combination with there being unlikely to be a notable rise in incidents associated with the installation of the offshore export cable(s) required for the Array.
  2. It is anticipated that the Inch Cape Offshore Wind Farm and the Seagreen 1A Project will be operational prior to commencement of construction of the Array with this also likely being the case for Berwick Bank Offshore Wind Farm noting timelines are less certain. Therefore, it is likely that the only additional project vessels on a cumulative basis will be those associated with the operation and maintenance of the Tier 1 projects, meaning it is likely that traffic volumes will be lower than during the construction phases, up until decommissioning. By extension, this is also likely to mean that risk of incident is lower.
  3. All offshore wind farms, including Inch Cape Offshore Wind Farm, Seagreen 1A Project and Berwick Bank Offshore Wind Farm, will also be required to produce and agree an ERCoP and SAR checklist with the MCA.
  4. Given the distance between Tier 1 offshore wind developments and the Array (in excess of 30 nm), there will be no direct cumulative impact on the ability to search the localised areas covered by the projects in a SAR operation.
Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on consideration of the historical incident data and the designed in measures in place including compliance with MGN 654.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be remote. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.

                        Tier 2

                        All phases
  1. All Tier 2 projects will be required to produce an ERCoP and agree a SAR checklist with the MCA, meaning that each individual project will have appropriate liaison measures with the MCA in place, and implement suitable SAR mitigations. The relevant MCA guidance (MCA, 2021b) also requires that individual ERCoPs consider SAR procedures and liaison on a cumulative basis.
  2. MCA guidance in the form of MGN 654 (MCA, 2021a) also dictates SAR design requirements for offshore wind farms. All Tier 2 projects will need to discuss and agree their layouts with the MCA, and these discussions will include consideration of other local offshore wind farms in proximity. This will ensure SAR operations can continue within the area, with SAR assets being able to access and search individual offshore wind farm layouts.
Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on consideration of the historical incident data and the designed in measures in place including compliance with MGN 654.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be remote. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP which is not significant in EIA terms.

                        Tier 3

                        All phases
  1. All Tier 3 projects will be required to produce an ERCoP and agree a SAR checklist with the MCA, meaning that each individual project will have appropriate liaison measures with the MCA in place, and implement suitable SAR mitigations. The relevant MCA guidance (MCA, 2021b) also requires that individual ERCoPs consider SAR procedures and liaison on a cumulative basis.
  2. MCA guidance in the form of MGN 654 (MCA, 2021a) also dictates SAR design requirements for offshore wind farms. All Tier 3 projects will need to discuss and agree their layouts with the MCA, and these discussions will include consideration of other local offshore wind farms in proximity. This will ensure SAR operations can continue within the area, with SAR assets being able to access and search individual offshore wind farm layouts.
Frequency of occurrence
  1. The frequency of occurrence is considered to be remote based on consideration of the historical incident data and the designed in measures in place including compliance with MGN 654.
Severity of consequence
  1. The severity of consequence is considered to be serious.
Significance of the effect
  1. Overall, the severity of consequence is deemed to be serious and the frequency of occurrence is considered to be remote. The effect will therefore be of tolerable significance and ALARP, which is not significant in EIA terms.
Further mitigation and residual effect
  1. No shipping and navigation mitigation is considered necessary because the likely effect in the absence of further mitigation (beyond the designed in measures outlined in section 13.10) is of tolerable significance and ALARP, which is not significant in EIA terms.

13.13.            Proposed Monitoring

13.13. Proposed Monitoring

  1. No monitoring is proposed for shipping and navigation.

13.14.            Transboundary Effects

13.14. Transboundary Effects

  1. A screening of transboundary impacts has been carried out and any potential for significant transboundary effects with regard to shipping and navigation from the Array upon the interests of European Economic Area (EEA) states has been assessed as part of the EIA. Transboundary impacts in terms of vessel routeing (including to international ports) are considered to have been assessed within section 13.11 (for the Array alone) and section 13.12 (on a cumulative basis). Individual transits may have the potential to be associated with vessels that are internationally owned or located, however, any such transits have been captured within the baseline assessment of vessel traffic as per section 13.7.1 (noting further detail and assessment is provided in the NRA (volume 3, appendix 13.1)).
  2. As such, no transboundary impacts other than those already assessed in section 13.11 and section 13.12 are anticipated.

13.16. Summary of Impacts, Mitigation, Likely Significant Effects and Monitoring

Information on shipping and navigation within the shipping and navigation study area was collected through consultation, assessment of the baseline environment (including vessel traffic, navigational features and incident rates) and numerical modelling. This information is summarised in Table 13.15   Open ▸ which presents a summary of the potential impacts, designed in measures and the conclusion of LSE1 in EIA terms in respect to shipping and navigation. The impacts assessed comprise:

  • increased vessel to vessel collision risk resulting from displacement (third-party to third-party);
  • displacement from adverse weather routeing;
  • increased vessel to vessel collision risk (third-party to project vessels);
  • vessel to structure allision risk;
  • reduced access to local ports and harbours;
  • loss of station;
  • reduction of underkeel clearance as a result of subsea infrastructure;
  • anchor interaction with subsea cables (including dynamic cabling);
  • anchor interaction with mooring lines; and
  • reduction in SAR capability.
  1. Overall, it is concluded that there will be no LSE1 arising from the Array during the construction, operation and maintenance or decommissioning phases.
  2. Table 13.16   Open ▸ presents a summary of the potential impacts, designed in measures and the conclusion of LSE1 on shipping and navigation in EIA terms. The cumulative effects assessed include:
  • increased vessel to vessel collision risk resulting from displacement (third-party to third-party);
  • displacement from adverse weather routeing;
  • increased vessel to vessel collision risk (third-party to Array vessels);
  • vessel to structure allision risk;
  • reduced access to local ports and harbours; and
  • reduction in SAR capability.
  1. Overall, it is concluded that there will be no likely significant cumulative effects from the Array alongside other projects/plans.
  2. No transboundary impacts other than those already assessed in section 13.11 and section 13.12 are anticipated. On this basis, no likely significant transboundary effects have been identified in regard to effects of the Array.
Table 13.15:
Summary of Likely Significant Environmental Effects, Secondary Mitigation and Monitoring

Table 13.15: Summary of Likely Significant Environmental Effects, Secondary Mitigation and Monitoring

Table 13.16:
Summary of Likely Significant Cumulative Environment Effects, Mitigation and Monitoring

Table 13.16: Summary of Likely Significant Cumulative Environment Effects, Mitigation and Monitoring

13.17.            References

13.17. References

Anatec (2016). Influence of UK Offshore Wind Farm Installation on Commercial Vessel Navigation: A Review of Evidence. Aberdeen: Anatec.

HM Government (2011). UK Marine Policy Statement. London: The Stationary Office.

IALA (2021a). IALA Recommendation O-139 on The Marking of Man-Made Offshore Structures. Edition 3.0. Saint Germain en Laye, France: IALA.

IALA (2021b). IALA Guideline G1162 The Marking of Offshore Man-Made Structures. Edition 1.0. Saint Germain en Laye, France: IALA.

IMO (1972/77). Convention on International Regulations for Preventing Collisions at Sea (COLREGs) – Annex 3. London: IMO.

IMO (1974). International Convention for the Safety of Life at Sea (SOLAS). London: IMO.

MCA (2022). Marine Guidance Note 372 Amendment 1 (Merchant and Fishing) Guidance to Mariners Operating in the Vicinity of UK OREIs. Southampton: MCA.

MCA (2014). National Contingency Plan: A Strategic Overview for Responses to Marine Pollution from Shipping and Offshore Installations. Southampton: MCA.

MCA (2021a). Marine Guidance Note 654 (Merchant and Fishing) safety of Navigation: offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response. Southampton: MCA.

MCA (2021b). Emergency Response Cooperation Plan: Template for Construction, Operations and Decommissioning phases. Southampton: MCA.

MCA and HSE (2017). Regulatory Expectations on Moorings for Floating Wind And Marine Devices. Amendment 2. Southampton: MCA.

MD-LOT (2023). Array Scoping Opinion. Edinburgh: MD-LOT.

RYA (2019a). The RYA’s Position on Offshore Renewable Energy Developments: Paper 1 (of 4) – Wind Energy. 5th revision. Southampton: RYA.

RYA (2019b). UK Coastal Atlas of Recreational Boating 2.1. Southampton: RYA.

Scottish Government (2015). Scotland’s National Marine Plan.

Scottish Government (2020). Scotland’s Sectoral Marine Plan.

UKHO (2021). Admiralty Sailing Directions North Sea (West) Pilot NP54. 12th Edition. Taunton: UKHO.

UKHO (2023). Admiralty Chart 273. Taunton: UKHO.

United Nations (1982). United Nations Convention on the Law of the Sea.

 

[1] C = Construction, O = Operation and maintenance, D = Decommissioning

[2] C = Construction, O = Operation and maintenance, D = Decommissioning

[3] C = Construction, O = Operation and maintenance, D = Decommissioning