1. Introduction

1.1.        Purpose

1.1. Purpose

  1. This outline Marine Pollution Contingency Plan (MPCP) provides the pollution response arrangements for the offshore infrastructure associated with the Ossian Offshore Wind Farm (hereafter referred to as “the Array”) during the construction and operation and maintenance phases.
  2. The overall purpose of this MPCP is to provide a list of procedures to safeguard the marine environment and respond to any potential accidental pollution event during the above phases of the Array. The procedures for safeguarding the marine environment during the decommissioning phase will be provided in a separate MPCP once the final decommissioning plan and methodologies are developed.
  3. This MPCP document represents best practice for pollution preparedness, and it is widely regarded within industry as best practice to have an MPCP in place where there is a risk of pollution, even when this is considered to be a low risk.
  4. Where a marine pollution incident is part of a wider emergency such as a fire or explosion, reference should also be made to the Emergency Response Co-operation Plan (ERCoP), which will be produced post consent.

1.2.        Project Background

1.2. Project Background

  1. The Array is an offshore wind farm off the east coast of Scotland, approximately 80 km south-east of Aberdeen from the nearest point (see Figure 1.1   Open ▸ ).
  2. The Array parameters have been selected from the Project Design Envelope (PDE) as assessed in the Array EIA Report. The Array will consist of the following:
  • up to 265 floating wind turbines (each comprising a tower section, nacelle, hub and three rotor blades) and associated floating foundations;
  • mooring and anchoring systems for each floating foundation;
  • connectors and ancillaries for mooring and anchoring systems, including buoyancy elements and clump weights;
  • up to six large Offshore Substation Platforms (OSPs), or up to three large OSPs and up to 12 small OSPs with fixed jacket foundations
  • scour protection per foundation for wind turbine anchoring systems;
  • scour protection for small and large OSP fixed foundations as required;
  • a network of dynamic/static inter-array cabling linking the individual floating wind turbines to each other and OSPs, and interconnector cables between OSPs (approximately 1,261 km of inter-array cabling and 236 km of interconnector cabling); and
  • discrete condition monitoring equipment (such as sensors, cameras, dataloggers etc.), as required for safe and efficient operation of the Array infrastructure.

Figure 1.1:
Location of the Array

Figure 1.1   Open ▸ : Location of the Array


1.3.        Scope

1.3. Scope

  1. This MPCP is an annex to the Array Environmental Management Plan (EMP) which covers measures to protect personnel and the marine environment relating to the marine works that will be undertaken as part of the Array (up to Mean High Water Springs (MHWS)) during the construction and operation and maintenance phases.
  2. The MPCP provides the following information and guidelines to aid a response to an accidental release of pollutants into the marine environment resulting from activities associated with the Array:
  • a risk assessment of the potential pollution sources and the likelihood of an accidental release (section 4.2); and
  • oil spill response procedures and actions (section 5.1).
  1. The information and guidelines presented in this outline MPCP will be reviewed in consultation with the Maritime and Coastguard Agency (MCA), Marine Directorate - Licencing Operations Team (MD-LOT) and Scottish Environment Protection Agency (SEPA) and will be re-submitted as a final draft prior to commencement of construction.
  2. All personnel and Contractors (including any sub-contractors) involved in the Array will be required to comply with this MPCP and will be provided with a copy of the MPCP and will be familiarised with the content, including roles and responsibilities, through toolbox talks.
  3. All vessel Contractors associated with the Array will also be expected to implement their own Ship-board Oil Pollution Emergency Plans (SOPEPs) (if applicable under the International Convention for the Prevention of Pollution from Ships (MARPOL) Convention (IMO, 2019) or their vessel specific spill plans in the event of an accidental marine pollution incident. This also applies to port side activities, with port authorities responsible for implementing specific spill/pollution plans.

1.5. Document Revision

  1. The Applicant will refine the MPCP before commencing construction and review this plan on an annual basis thereafter, or after significant legislative or procedural changes that would require updates to be made to this MPCP.
  2. In addition, the MPCP will be further refined in preparation for the operation and maintenance phase of the Array.

2.             Summary of Designed-In Measures, Mitigation and Monitoring Included in the Array EIA Report

2. Summary of Designed-In Measures, Mitigation and Monitoring Included in the Array EIA Report

  1. Table 2.1   Open ▸ provides a summary of the mitigation measures identified in the Array EIA Report relevant to the MPCP.

 

Table 2.1:
Mitigation Measures Relevant to the MPCP

Table 2.1: Mitigation Measures Relevant to the MPCP

3.             Roles and Responsibilities

3. Roles and Responsibilities

3.1.        The Applicant

3.1. The Applicant

  1. The Applicant will contractually require Contractors and Subcontractors to take responsibility for pollution events originating from the Array.

3.2.        The Applicant Environmental Manager

3.2. The Applicant Environmental Manager

  1. The Applicant Environmental Manager for each phase of the Array is responsible for the overall preparation and implementation of the MPCP, including the following duties:
  • preparing and maintaining the MPCP to an agreed schedule; and
  • ensuring Contractors develop MPCPs (which should include adequate pollution prevention and spill response procedures), and ensuring that these are reviewed to an agreed schedule and implemented throughout operations.
  1. The Applicant Environmental Manager will review and update the MPCP as necessary during the construction phase of the Array to include any new information. Furthermore, this MPCP will also be reviewed and amended after construction is completed, to make it applicable to the operation and maintenance phase of the Array.
  2. The Applicant will appoint an Environmental Clerk of Work (ECoW), Marine Coordinator and a dedicated Spill Response Contractor for the Array.
  3. Following completion of construction, the Applicant Environmental Manager will ensure the MPCP is reviewed and amended annually or after significant legislative or procedural changes that would require updates to be made to this MPCP, as necessary for the operation and maintenance phase of the Array.
  4. The Applicant Environmental Manager will review and update this MPCP as required and to the agreed schedule during the construction phase of the Array (e.g. to take into account any new information, that may become available).
  5. In the event of any oil or chemical spill to the marine environment, following the completion of remedial action, an internal meeting will be held to close out the incident and ensure any lessons are learnt, which will be led by the Applicant Environmental Manager.

3.3.        The Environmental Clerk of Works

3.3. The Environmental Clerk of Works

  1. The Applicant will be required to appoint an ECoW, whose main responsibilities will include:
  • quality Assurance and approval of the Applicants MPCP and ensuring compliance with consent conditions, the EMP and other relevant consent plans;
  • review and approve all updates and amendments to the MPCP made by the Environmental Manager during all phases of the Array;
  • inductions and toolbox talks to Contractors and Subcontractors to ensuring implementation of the MPCP in accordance with consent conditions;
  • managing ongoing Contractor spill response (through liaison with Contractor);
  • ensuring delivery and compliance with this MPCP, including named personnel, appropriate resourcing and required processes are in place;
  • ensuring delivery of this MPCP in compliance with consent conditions, the EMP and other relevant consent plans as well a relevant legislation and policy; and
  • notifying statutory bodies of a spill, such as MCA, MD-LOT and SEPA and any relevant local authorities.

3.4.        Marine Coordinator

3.4. Marine Coordinator

  1. A Marine Coordinator will be appointed by the Applicant before construction at the Array commences. As well as coordinating the day to day vessel activity at the Array, the Marine Coordinator will be the main point of contact should an emergency or pollution event occur.
  2. As such, the Marine Coordinator will assist with the ongoing response in the event of a pollution incident from a vessel or vessel related activity, ensuring close communication between the Applicant and relevant Contractors/Subcontractors.
  3. The Marine Coordinator will also oversee the pollution response and any required clean-up operations should a pollution event occur from an Array installation activity.

3.5.        Contractor and Subcontractor

3.5. Contractor and Subcontractor

  1. Most of the construction and operation and maintenance activities at the Array will be carried out by Contractors and/or Subcontractors, thus the Applicant will contractually require they are familiar with this MPCP.
  2. Furthermore, each Contractor/Subcontractor will be expected to prepare their own MPCP before activities commence at the Array. The Contractor/Subcontractor MPCP will be expected to comply with this MPCP and also to prepare their own spill response arrangements, including reporting and response procedures that ‘bridge’ to this MPCP. Each Contractor/Subcontractor will be expected to maintain a spill risk register for all equipment to be used at the Array.
  3. The Contractor/Subcontractor MPCP will be expected to be submitted to and reviewed/approved by the Applicant before being implemented at the Array. Once approved, it is expected it will be subject to an appropriate six-monthly review/update cycle and re-approved by the Applicant following each updated prior to implementation.
  4. All Contractor/Subcontractors will be expected to ensure relevant personnel are trained in pollution prevention and response and that vessel contain appropriate pollution response equipment.
  5. All vessels working in the Array will be subject to the requirements of the Applicant Vessel Inspection Procedure. In addition to this all vessels under the control of the Contractor/Subcontractor will be expected to have a SOPEP or equivalent vessel-specific spill plan (i.e. for spills originating from a vessel or as a result of activities carried out by the Contractor/Subcontractor).
  6. The Applicant will contractually require the Marine Coordinator to be notified by the Contractor/Subcontractor of any pollution incidents at the Array, together with any proposed response procedures.

3.6.        Spill Response Contractor

3.6. Spill Response Contractor

  1. An oil spill response Contractor must be in place before construction commences at the Array.
  2. During the construction phase, the ECoW and the oil spill response Contractor will be required to provide response capabilities in accordance with the maximum adverse scenario associated with the Contractor/Subcontractor scope of work.
  3. During the operation and maintenance phase, the ECoW and the oil response Contractor will provide response capabilities, coordinating as necessary with the Environmental Manager, in relation to the maintenance activities carried out at the Array.
  4. In the unlikely event of a Tier 2/3 spill occurring, the decision on whether to engage a Tier 2/3 Contractor will be made by the Applicant in consultation with the Maritime and Coastguard Agency (MCA) and MDLOT.

3.7.        Maritime and Coastguard Agency

3.7. Maritime and Coastguard Agency

  1. The MCA is designated as the UK Competent Authority for counter pollution response at the national level and is the custodian of the National Contingency Plan (NCP) which includes arrangements for dealing with pollution, or the threat of pollution, from shipping and offshore installations. The national regime lays down no rigid criteria for NCP activation however it is considered very unlikely that the NCP will be activated for spills originating from activities related to the Array due to the relatively low risk of spills from offshore wind farm activities.

4.             Potential Spill Sources and Control Measures

4. Potential Spill Sources and Control Measures

4.1.        Potential Spill Sources and Control Measures

4.1. Potential Spill Sources and Control Measures

  1. Construction and operation and maintenance works will be undertaken in such a manner as to minimise the risk of spills and accidental pollution events.
  2. Spills are considered most likely to occur during transfer of hydrocarbons and chemicals offshore (e.g. during refuelling operations, or in the event of a leak within equipment within the Array). However, due to measures adopted such as operating procedures, toolbox talks and experience working in the marine environment, the majority of spills associated with the Array are considered likely to be small (Tier 1).
  3. The Contractor/Subcontractor MPCP will be requested to include the following information:
  • an inventory of the types of pollutants (particularly hydrocarbons) to be used during the construction and/or operation of the Array. These should include volumes, type and source for each of the pollutants identified (e.g. hydraulic oils, lubricants etc); and
  • preventative measures relevant to the activities to be undertaken at the Array.
  1. A register of all the vessels involved in construction and operation activities at the Array shall be developed and updated by the Marine Coordinator. This register will list the types and volumes of hydrocarbons carried on board vessels associated with the Array.
  2. The risk of spillage and pollution will be minimised by using correct procedures during the construction and operation and maintenance phases. Potential spill risks and control measures will be identified using planning tools such as:
  • programme review meetings (involving relevant Contractors);
  • pre-commencement meetings to review the final work programme(s); and
  • preparation of Risk Assessment Method Statements (RAMS) for all operations including hazard and risk identification. This will test the work programme for likelihood and severity of all potential risks and to identify appropriate control measures.
  1. Section 4.2 contains information regarding pollution sources and risk assessment, together with proposed control measures.

4.2.        Pollution Sources and Risk Assessment

4.2. Pollution Sources and Risk Assessment

4.2.1.    Tier Classification

4.2.1. Tier Classification

  1. Potential spill scenarios will be dictated by the chemical inventories (including hydrocarbons) associated with activities associated with the Array.
  2. Levels of response for oil spill are generally divided into three tiers, depending on the severity of the spill, the resources required to deal with the spill, and the potential impact on environmental and human receptors. Applying a tiered approach ensures the appropriate resource can be made available for potential pollution incidents. These tiers are commonly described as follows and are illustrated in Figure 4.1   Open ▸ :
  • Tier 1 response is that which is immediately available on site, geared for the most likely and low risk spill. Generally, Tier 1 responses will be managed by the Contractor/Subcontractor;
  • Tier 2 response is for less frequently anticipated spills of larger size and for which external resources at a regional level will be required to assist in monitoring and clean-up; and
  • Tier 3 response is in place for the very rarely anticipated spill of major proportions and which will possibly require national and international resources to assist in protecting vulnerable areas and in the clean-up.

Figure 4.1:
Tier Definition (based on MMO, 2020)

Figure 4.1: Tier Definition (based on MMO, 2020)

 

  1. Tier 3 scenario usually covers an exceptionally large volume of spilled oil, usually a rare but highly significant event, such an oil well blowout or major spill from a ship. However, a Tier 3 response may also be required for smaller spills which would usually fall under Tier 2, but if located in highly sensitive areas (e.g. near to designated sites with features vulnerable to the impact of accidental pollution), or when highly specialised strategies to deal with the spill may be needed and are not available locally.

4.2.2.    Array Potential Spill Scenarios and Control Measures

4.2.2. Array Potential Spill Scenarios and Control Measures

  1. Table 4.1   Open ▸ describes the potential spill scenarios and control measures identified for the Array. This table will be refined prior to commencement of construction and adapted accordingly for the relevant Contractor MPCP and as much is subject to change once further detail is available. Furthermore, the risk assessment will be reviewed and updated annually or after significant legislative or procedural changes as necessary after completion of the construction phase to verify its relevance before the operation and maintenance phase of the Array commences.
  2. The main source of hydrocarbons associated with the Array will include the following:
  • wind turbines: synthetic oil, hydraulic oil, gear oil and diesel fuel; and
  • OSPs: diesel fuel, transformer coolant oil, HVAC coolant.
  1. The volumes of these will be limited to the bunkering capabilities of the vessels. The realistic maximum adverse scenario would be a complete loss of fuel inventory from two large vessels (either as a result of a two vessel collision or a vessel to wind farm allision).
Table 4.1:
Potential Spill Scenarios and Control Measures for the Array

5.             Response Procedures and Checklists

5. Response Procedures and Checklists

5.1.        Pollution Incident Response Procedure

5.1. Pollution Incident Response Procedure

5.1.1.    Introduction

5.1.1. Introduction

  1. Any spill (actual or likely) into the marine environment, irrelevant of its size and whether it arises from the activities at the Array or not, must be reported, following the procedures set out in sections 5.1.2 to 5.1.4, whilst a Contractor or Subcontractor is working on the Array.
  2. In the event of a spill, priority should be given to taking measures to ensure the safety of personnel, offshore installations and vessels, and to prevent escalation of the spill.
  3. Should the spillage be part of a wider emergency, such as fire or explosion, reference should also be made to the ERCoP, which will be produced post consent.

5.1.2.    Spills Originating from a Vessel – Response and Notification Overview

5.1.2. Spills Originating from a Vessel – Response and Notification Overview

  1. In the event of a marine pollution incident (hydrocarbon or chemical), where the spill originates from a vessel or a vessel related activity, during construction or operation and maintenance at the Array, the steps described below should be followed:
  • report the spill to the Vessel Master as soon as it is observed;
  • the Contractor/Subcontractor Vessel Master will report the spill as soon as it is safe to do so, to the Coastguard Operations Centre (CGOC) via phone, and then to the Marine Coordinator via phone. Verbal communication should be followed up when practicable with the submission by the Contractor/Subcontractor Vessel Master of a Marine Pollution Report (POLREP) via email (or fax) to the CGOC and the Marine Coordinator, who in turn will notify the Applicant personnel (see volume 4, appendix 22); and
  • the Contractor/Subcontractor responsible for the vessel from which the spill has originated will engage the vessel SOPEP and assume primacy for the incident ensuring ongoing reporting on spill status, as necessary, and initiating response or clean-up operations as required. The relevant Contractor/Subcontractor, as the primary responder, will request support from a specialist spill response contractor as required. The Marine Coordinator will provide a supporting role and assist with communication throughout an incident.
  1. In the very unlikely event that a regional or national (Tier 2 or 3) response is required, the MCA may take charge of the situation and implement the National Contingency Plan (NCP) (MCA, 2014).

5.1.3.    Spills Originating from an Installation Associated with the Array – Response and Notification Overview

5.1.3. Spills Originating from an Installation Associated with the Array – Response and Notification Overview

  1. The following steps should be followed when the spill originates from an installation associated with the Array:
  • report the spill to the Marine Coordinator as soon as it is observed;
  • the Marine Coordinator will report the spill as soon as it is safe to do so, to the Coastguard Operations Centre (CGOC) via phone, and then to The Applicant Environmental Manager via phone. Verbal communication should be followed up when practicable with the submission by the Marine Coordinator of a Marine POLREP via email (or fax) to the CGOC; and
  • the Marine Coordinator will engage the MPCP and assume primacy for the incident. The Marine Coordinator will be responsible for ongoing reporting on spill status and coordinate the initial response with the spill observer who may utilise spill kits on the offshore installation. The primary responder will request support from a specialist spill response Contractor as required.
  1. The type and volume of hydrocarbons and chemicals on the wind turbines and OSPs/offshore convertor station platforms are not considered to warrant a Tier 2 or Tier 3 response ( Table 4.1   Open ▸ ) due to volume and type of chemical. It is therefore not anticipated that the implementation of an NCP would be required. Nonetheless, the MCA will be kept informed by verbal communications and through ongoing submission of the POLREP.

5.1.4.    Spills within a Port

5.1.4. Spills within a Port

  1. For Port/Harbour spills the Contractor/Subcontractor will contact the relevant Port/Harbour Authority in the first instance and follow all port processes as advised. Each Contractor MPCP will provide details of all ports/harbour authorities of relevance.
  2. The Contractor/Subcontractor will provide details in advance of their works, of the main ports/harbour authorities anticipated to be used whilst working on the Array, therefore contact detail will be updated by the Contractor/Subcontractor. All incidents that occur whether in the Array working area or not, must be notified to The Applicant Environmental Manager and Marine Coordinator.

5.2.        Reporting Requirements

5.2. Reporting Requirements

  1. There is a requirement for all Employees, Contractors and Subcontractors to report all accidents, incidents and hazards to the Applicant Environmental Manager and Marine Coordinator.
  2. Significant or potentially significant incidents (including marine incidents) are required to be immediately reported and escalated through the business management chain within 30 minutes of their occurrence or when safe to do so.
  3. In the event of a pollution incident, the Spill Observer shall notify the Applicant Environmental Manager. The Applicant Environmental Manager shall then notify the Vessel master and Marine Coordinator. The Marine Coordinator shall then notify the CGOC and the MCA.
  4. If the spill originates from a vessel, or from operations taking place on a vessel, the Spill Observer shall report it directly to the Vessel Master. The Vessel Master shall then notify the Applicant Environmental Manager and Marine Coordinator. The Vessel Master shall also notify the CGOC and the MCA.

5.2.1.    Statutory Reporting Requirements

5.2.1. Statutory Reporting Requirements

  1. There is a statutory requirement to report marine pollution incidents to Marine Scotland (HM Government, 2018) and SEPA for coastal waters (Scottish Government, 2022). There is also a requirement to report any spill incident to the Applicant 24-hour reporting line within 30 minutes of the incident occurring.
  2. The flow chart in Figure 5.1   Open ▸ should be followed for all responses.

Figure 5.1:
Reporting Requirements for any Potential Spills at the Array

Figure 5.1: Reporting Requirements for any Potential Spills at the Array

 

5.2.2.    Response Checklists

5.2.2. Response Checklists

  1. Table 5.1   Open ▸ to Table 5.4   Open ▸ provide key actions and notification for key personnel identified in Figure 5.1   Open ▸ with which they would be expected to comply.

 

Table 5.1:
Spill Observer

Table 5.1: Spill Observer


Table 5.2:
Applicant Environmental Manager or Vessel Master

Table 5.2: Applicant Environmental Manager or Vessel Master


Table 5.3:
Marine Coordinator

Table 5.3: Marine Coordinator

 

Table 5.4:
Harbour Master

Table 5.4: Harbour Master

 

5.3.        Response Strategies

5.3. Response Strategies

5.3.1.    Response Strategies for Tier 1 Incidents

5.3.1. Response Strategies for Tier 1 Incidents

  1. The key response strategy for Tier 1 spills will be to allow natural dispersion, together with monitoring and evaluation using a small vessel. This is the best option for Tier 1 spills of water-soluble chemicals, or of light oils such as diesel or hydraulic oil. Natural dispersion can be encouraged using a technique called ‘prop-washing’.

5.3.2.    Response Strategies for Tier 2/3 Incidents

5.3.2. Response Strategies for Tier 2/3 Incidents

  1. It is expected that any spills associated with the Array will be Tier 1 spills due to the small inventories of oil/chemicals and the low risk nature of activities to be carried out.
  2. In the event of a Tier 2 incident, it is expected Marine Scotland will request assistance from the relevant Port Authority with regards to access to the stockpile of pollution response equipment and the relevant Port Authority as an Oil Spill Response Co-operative known as the Oil Clean Up Committee. Access to this stockpile is by mutual agreement between Marine Scotland and the relevant Port Authority.
  3. The decision on whether to engage a Tier 2/3 contractor would likely be made by relevant Port Authority in consultation with Marine Scotland. The relevant Port Authority Tier 2 contractor will be confirmed post consent. They will store and maintain a stockpile of equipment. In the event of a Tier 2 incident the contractor Response will be managed by the relevant Port Authority (in ongoing consultation with Marine Scotland where required).
  4. Figure 5.2   Open ▸ details the environmental sensitivities in the vicinity of the Array that will require consideration during a Tier 1 to 3 spill.

Figure 5.2:
Protected Areas in the Vicinity of the Array

Figure 5.2 Protected Areas in the Vicinity of the Array


6.             Spill Risk Proforma

6. Spill Risk Proforma

Spill Risk Proforma – to be completed for each new equipment deployment

Name of Assessor:

 

Date:

 

Equipment Type/Brief Description of Equipment:

 

 

Liquid Inventories

 

 

Product Name

Product type

Volume (litres)

Location

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Reviewed by Operations Manager:

 

Date:

 

Information Accepted by Marine Scotland?

 

Yes – mark as approved                      

No – explain to proponent what further information is needed

Signed off by Operations Manager:

 

Name:

 

Date:

 

7.             Spill Assessment Checklist

7. Spill Assessment Checklist

  1. To be completed by the Applicant Environmental Manager or Vessel Master.

 

Spill Assessment Checklist

This checklist is designed to assist those personnel who have the responsibility of assessing a spill incident. These personnel are likely to be:

Applicant Environmental Manager

Vessel Master.

Step

Guidance

Determine Essential Details

Location of pollution incident;

Source of spill;

Oil/chemical type;

Extent of spill;

Time of incident;

Potential hazardous circumstances;

Any other relevant information (particularly: is spill contained or ongoing?).

Assess Safety Hazards

Until otherwise established, assume an oil spill is giving off potentially dangerous volatile organic compounds (VOCs) (i.e. hydrocarbon vapours).

ELIMINATE IGNITION SOURCES

Approach spill from upwind to reduce effects of vapours.

APPROACH ONLY IF SAFE TO DO SO!

Determine Spill Source

If source unknown, investigate with care.

Instigate actions to stop spillage at source.

IF SAFE TO DO SO!

Estimate Quantity

Estimate quantity of release if exact amount unknown.

Determine movement

Determine direction and speed of spill movement based upon the prevailing wind and sea conditions.

Assess prevailing and if possible future weather conditions

Determine:

Wind speed and direction;

State of tide;

Current speed and direction; and

Sea state.

 

8.             Pollution Incident Log Sheet

8. Pollution Incident Log Sheet

  1. An incident log must be completed by all personnel involved in the spill response.

 

Name:
Team:
Role:
Location:

 

Date/Time:

Communication/Action Taken/Notes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

9.             Contacts Directory

9. Contacts Directory

Organisation

Contact

Telephone (office hours)

24 hr Telephone

Mobile/Pager/Emails

The Applicant

Applicant Environmental Manager

 

 

 

 

Marine Coordinator

 

 

 

 

Marine Directorate

Incident Communication Centre

 

 

 

 

Coastguard and MCAs

Aberdeen CGOC

 

 

 

 

MCA

 

 

 

 

Port Authorities

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Other Installations

 

 

 

 

 

Environmental Agencies

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Emergency Services

Ambulance

 

 

 

 

Fire

 

 

 

 

 

 

 

 

Pollution

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Local Authorities

 

 

 

 

 

 

 

 

 

 

Other Contacts (for information, advice or appointment of ad-hoc spill response contractor)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10.     References

10. References

HM Government (2018). Guidance - How to respond to marine pollution incidents. Available at: How we respond to marine pollution incidents - GOV.UK (www.gov.uk). Accessed on: 25 April 2024.

MCA (2014). The National Contingency Plan. A Strategic Overview for Responses to Marine Pollution from Shipping and Offshore Installations. Available at: National Contingency Plan (NCP) - GOV.UK (www.gov.uk). Accessed on: 25 April 2024.

MMO (2020). Marine Pollution Contingency Plan. Available at: Marine_Pollution_Contingency_plan.pdf (publishing.service.gov.uk). Accessed on: 25 April 2024.

Scottish Government (2022). Policy – Pollution. Available at: Pollution - gov.scot (www.gov.scot). Accessed on: 25 April 2024.