6. Economic Impact of PDE Option 3 (Commitment)

6.1. Construction

6.1.1. Ossian Impact

  1. Based on the estimated expenditure for Ossian as a whole, the technical expert’s model of costs and the information provided in the SCDS it was assumed that under PDE Option 3 the construction phase spend in Scotland could be £3.7 billion (35% of total expenditure) and in the UK it could be £4.7 billion (45%), which is shown in Table 6.1. The largest expenditure is associated with the manufacture of floating foundations.

 

Table 6.1: PDE Option 3: Ossian Construction Spending by Category, Scotland and the UK

Parameters

Scotland

UK (Inc. Scotland)

Total (Scotland, rUK and rWorld)

Wind Turbine

 £777 m

 £1,217 m

 £3,593 m

Floating Foundation Manufacturing

 £1,833 m

 £1,833 m

 £2,234 m

Cables Supply

 £0 m

 £147 m

 £1,265 m

Offshore Cable Installation

 £187 m

 £262 m

 £1,249 m

Floating Foundations Installation

 £180 m

 £215 m

 £505 m

OSP

 £339 m

 £433 m

 £471 m

Development and Consenting Services

 £313 m

 £313 m

 £455 m

Floating Mooring Systems

 £78 m

 £156 m

 £390 m

Onshore Substation

 £0 m

 £129 m

 £280 m

Onshore Cable Installation

 £0 m

 £34 m

 £34 m

Operation and Maintenance Base

 £7 m

 £7 m

 £7 m

Total

 £3,715 m

 £4,747 m

 £10,483 m

Total (%)

35%

45%

100%

 

  1. Applying turnover per employee and turnover/GVA ratios for the relevant sectors it was estimated that the direct economic of the Array could be £1.5 billion and 22,180 years of employment in Scotland and £1.9 billion GVA and 27,790 years of employment in the UK (Table 6.2).

 

Table 6.2: PDE Option 3: Ossian Construction Direct Economic Impact, Scotland and the UK

Parameters

Scotland

UK

 

GVA

Years of Employment

GVA

Years of Employment

Wind Turbine

 £314 m

 4,710

 £486 m

 7,260

Floating Foundation Manufacturing

 £723 m

 10,430

 £723 m

 10,430

Cables Supply

 £0 m

 0

 £54 m

 750

Offshore Cable Installation

 £48 m

 590

 £67 m

 820

Floating Foundations Installation

 £74 m

 1,290

 £86 m

 1,450

OSP

 £185 m

 2,890

 £236 m

 3,690

Development and Consenting Services

 £111 m

 1,730

 £111 m

 1,730

Floating Mooring Systems

 £35 m

 530

 £70 m

 1,050

Onshore Substation

 £0 m

 0

 £41 m

 470

Onshore Cable Installation

 £0 m

 0

 £11 m

 120

Operation and Maintenance Base

 £2 m

 30

 £2 m

 30

Total

 £1,493 m

 22,180

 £1,887 m

 27,790

 

  1. Applying GVA and employment multipliers it was therefore estimated that the total economic impact could be £2.5 billion GVA and 37,170 years of employment in Scotland, and £4.9 billion GVA and 70,310 years of employment in the UK (Table 6.3) (Table 6.4).

 

Table 6.3: PDE Option 3: Ossian Construction GVA impact, Scotland and the UK

Parameters

Scotland

UK

Direct GVA

 £1,493 m

 £1,887 m

Indirect GVA

 £562 m

 £1,537 m

Induced GVA

 £462 m

 £1,507 m

Total GVA

 £2,517 m

 £4,932 m

 

Table 6.4: PDE Option 3: Ossian Construction Employment impact, Scotland and the UK

Parameters

Scotland

UK

Direct Years of Employment

 22,180

 27,790

Indirect Years of Employment

 8,950

 21,080

Induced Years of Employment

 6,040

 21,440

Total Years of Employment

 37,170

 70,310

 

6.1.2. Array Impact

  1. For the Array it was estimated that the total spend could be £8.0 billion, of which £3.4 billion (43%) could be secured in Scotland and £4.2 billion (52%) could be secured in the UK (Table 6.5).

 

Table 6.5: PDE Option 3: Array Construction Spending by Category, Scotland and the UK

Parameters

Scotland

UK (Inc. Scotland)

Total (Scotland, rUK and rWorld)

Wind Turbine

 £777 m

 £1,217 m

 £3,593 m

Floating Foundation Manufacturing

 £1,833 m

 £1,833 m

 £2,234 m

Offshore Cable Installation

 £47 m

 £66 m

 £312 m

Cables Supply

 £0 m

 £87 m

 £175 m

OSP

 £180 m

 £215 m

 £505 m

Development and Consenting Services

 £214 m

 £273 m

 £297 m

Floating Mooring Systems

 £78 m

 £156 m

 £390 m

Floating Foundations Installation

 £313 m

 £313 m

 £455 m

Operation and Maintenance Base

 £7 m

 £7 m

 £7 m

Total

 £3,449 m

 £4,167 m

 £7,968 m

Total (%)

43%

52%

100%

 

  1. Applying turnover per employee and turnover/GVA ratios for the relevant sectors it was estimated that the direct economic impact of the Array could be £1.4 billion and 20,680 years of employment in Scotland and £1.7 billion GVA and 24,910 years of employment in the UK (Table 6.6).

 

Table 6.6: PDE Option 3: Array Construction Direct Economic Impact, Scotland and the UK

Parameters

Scotland

UK

 

GVA

Years of Employment

GVA

Years of Employment

Wind Turbine

 £314 m

 4,710

 £486 m

 7,260

Floating Foundation Manufacturing

 £723 m

 10,430

 £723 m

 10,430

Offshore Cable Installation

 £12 m

 150

 £17 m

 200

Cables Supply

 £0 m

 0

 £32 m

 430

OSP

 £74 m

 1,290

 £86 m

 1,450

Development and Consenting Services

 £116 m

 1,820

 £149 m

 2,320

Floating Mooring Systems

 £35 m

 530

 £70 m

 1,050

Floating Foundations Installation

 £111 m

 1,730

 £111 m

 1,730

Operation and Maintenance Base

 £2 m

 30

 £2 m

 30

Total

 £1,388 m

 20,680

 £1,676 m

 24,910

 

  1. Applying GVA and employment multipliers it was therefore estimated that the Array’s economic impact could be £2.3 billion GVA and 34,750 years of employment in Scotland, and £4.4 billion GVA and 62,640 years of employment in the UK (Table 6.7) (Table 6.8).

 

Table 6.7: PDE Option 3: Array Construction Total GVA impact, Scotland and the UK

Parameters

Scotland

UK

Direct GVA

 £1,388 m

 £1,676 m

Indirect GVA

 £528 m

 £1,349 m

Induced GVA

 £432 m

 £1,339 m

Total GVA

 £2,348 m

 £4,365 m

 

Table 6.8: PDE Option 3: Array Construction Total Employment impact, Scotland and the UK

Parameters

Scotland

UK

Direct Years of Employment

 20,680

 24,910

Indirect Years of Employment

 8,420

 18,590

Induced Years of Employment

 5,660

 19,150

Total Years of Employment

 34,750

 62,640

 

  1. The spend at the primary construction port(s) is expected to be around £217 million, which would require a significant workforce, with an estimated peak direct employment of 340 jobs (Table 6.9). The largest contract is expected to be associated with marshalling harbour (£162 million).

 

Table 6.9: PDE Option 3: Array Construction Port Impact by Category

Parameters

Total Investment

Port Spend

Employment

Peak Employment

Wind Turbine Assembly

£121 m

£17 m

80

20

Marshalling Harbour

£162 m

£162 m

1,310

290

Offshore Logistics

£9 m

£9 m

80

20

Anchor Installation

£142 m

£28 m

70

10

Total

£434 m

£217 m

1,540

340